MahaRERA Property Intelligence · Pune
P52100001521 · KHARADI · promoter Marvel Realtors And
| MahaRERA registration | P52100001521 |
| Registered on | 28 Jul 2017 |
| Promoter-declared completion | 31 Mar 2024 |
| Current status | Certificate Signed |
| Against today | about 28 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Marvel Realtors And is the promoter of record on 54 projects, of which 32 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
Of 82 homes filed with MahaRERA, 76 are sold/booked (62 with registered agreements + 14 booked) and 6 remain available (~93% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹184.59 Cr in agreement value so far. Of that, ₹135.18 Cr (~73%) is already collected, ₹49.41 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 76 registered agreements, the effective carpet rate is ₹11,198/sqft (typical range ₹10,165–₹12,620) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:
| Floor | Unit | Carpet | Reckoner value |
|---|---|---|---|
| Floor 1 | 101 | 1,792 sqft (166.5 sqm) | ₹1.31 Cr |
| Floor 1 | 101 | 2,405 sqft (223.47 sqm) | ₹1.76 Cr |
| Floor 1 | 102 | 2,949 sqft (274 sqm) | ₹2.15 Cr |
| Floor 1 | 102 | 1,633 sqft (151.67 sqm) | ₹1.19 Cr |
| Floor 16 | 1601 | 3,153 sqft (292.94 sqm) | ₹2.30 Cr |
| Floor 3 | 301 | 2,271 sqft (210.99 sqm) | ₹1.66 Cr |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25 and 82 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| A | 1 | G+25 | 41 | 30 Dec 2021 |
| B | 1 | G+25 | 41 | 30 Dec 2021 |
Unit mix on the filing: 82 residential.
22 complaints are on the MahaRERA record for this project, with orders passed in 22. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC005000000010472 | 03/11/2017 | Priya Eidnani vs Marvel Realtors | order passed |
| CC005000000011069 | 04/03/2018 | Priya Eidnani vs Vishwajeet Jhavar | order passed |
| CC005000000011446 | 20/04/2018 | Asheet Pasricha and Ors vs Marvel Promoters and Developers (Pune) Pvt Ltd | order passed |
| CC005000000023365 | 25/08/2019 | Mrs. Arnaz Gautam Dembla vs Marvel promoters and developers pune pvt ltd and others | order passed |
| CC005000000023366 | 25/08/2019 | Sujata A Mangharam vs marvel promoters and developers pune pvt ltd | order passed |
| CC005000000023368 | 25/08/2019 | srinivasa rao duddupudi vs marvel promoters and developers pune pvt ltd and others | order passed |
| CC005000000023395 | 04/09/2019 | Marvel Aquanas Cooperative Housing Society Limited through secretary (society) vs Marvel Promoters and Developers Pune Pvt Ltd and Others | order passed |
| CC005000000064253 | 08/06/2020 | SAPNA RATAN vs Marvel Realtors and Developers Limited | order passed |
| CC005000000064257 | 09/06/2020 | SURESH BHIMRAO DESHMUKH vs Marvel Realtors and Developers Limited | order passed |
| CC005000000064259 | 10/06/2020 | RAJESH RAJAN OVALEKAR vs Marvel Realtors and Developers Limited | order passed |
| CC005000000064260 | 10/06/2020 | MARVEL ACQUANAS COOPERATIVE HOUSING SOCIETY LIMITED (society) vs Marvel Realtors and Developers Ltd. | order passed |
| CC005000000075129 | 28/01/2021 | Chaitanya Kamal Infracon LLP vs Marvel Realtors and Developers Ltd. | order passed |
| CC005000000022770 | 09/03/2019 | SADHNA RAJANI vs MARVEL PROPERTERS AND DEVELOPER | order passed |
| CC005000000022945 | 25/05/2019 | RAJKUMAR RAJABHAU SHINDE vs MARVEL PROMOTERS AND DEVELOPERS (PUNE) PVT LTD | order passed |
| CC005000000054158 | 17/03/2020 | Sameer Jabbar Sayed vs Marvel Promoters and Developers (Pune) Pvt. Ltd, | order passed |
| CC005000000085534 | 10/05/2021 | MARVEL ACQUANAS COOPERATIVE HOUSING SOCIETY LTD (society) vs MARVELPROMOTERS AND DEVELOPERS (PUNE) PVT LTD., | order passed |
| CC005000000269342 | 25/08/2023 | MARVEL CHSL (society) vs Marvel Realtors and Developers Pvt Ltd | order passed |
| CC005000000471314 | 17/07/2024 | MARVEL CHSL (society) vs MARVEL REALTORS AND DEVELOPERS LTD | order passed |
| CC005000000106512 | 19/01/2022 | Smt. Neelam Sushil Kapur vs Marvel Promoters and Developers (Pune) Pvt. Ltd | order passed |
| CC005000000106767 | 16/03/2022 | Grishmi Deepak Ghodke vs Marvel Realtors and Developers | order passed |
| CC005000000167398 | 26/07/2022 | Marvel Realtors and Developers Limited vs Mrs. Sadhana Ashokkumar Rajani Through her Constituted POA Mr. Vikas Pawar | order passed |
| CC005000000167582 | 15/09/2022 | Santosh Sethuraman vs Marvel Realtors and Developers Ltd., | order passed |
⚠ A co-operative housing society is the complainant here (Marvel Aquanas Cooperative Housing Society Limited through secretary) and MahaRERA has already passed an order. On a redevelopment, that is the LANDOWNER society in dispute with its developer — a different order of risk from a single buyer's grievance, because it can touch the development rights, the society's consent, and ultimately the title to your flat. Have your lawyer read this order and the development agreement together before you commit.
The promoter has had the MahaRERA completion deadline formally extended 4 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 31 Mar 2024 | 31 Mar 2024 | 1. That there are two residential buildings in the project namely ‘Marvel Aquanas’. The construction of the buildings are completed near about 80 to 83 % and only the internal cons |
| 31 Mar 2024 | 31 Oct 2022 | The project, namely Marvel Aquanus, comprising of 82 flats (i.e. Sold units – 54 and Unsold units - 28). We have completed 90 % of the work, and some work is remaining due to an un |
| 31 Mar 2024 | 30 Apr 2023 | Delay due to covid and other unavoidable reasons |
| 31 Mar 2024 | 30 Dec 2020 | Adverse market condition and money dismemberment issue form bank |
Located at KHARADI, S.No. 69 / 4 (P) + S.No. 69 / 5 (P), Pune City, Pune, 411014. Per the filed land record, the plot is bounded to the north by AMENITY AREA, to the south by 30 MTR DP ROAD, to the east by PLOT BOUNDARY and to the west by PLOT BOUNDARY. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Kharadi / EON IT Park | 2 km |
| Magarpatta / Hadapsar IT | 5 km |
| Pune Int'l Airport (Lohegaon) | 5 km |
| Pune Junction / city centre | 9 km |
| Baner–Balewadi belt | 19 km |
| Hinjewadi Rajiv Gandhi IT Park | 24 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in MARVEL AQUANAS?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Marvel Realtors AND Developers LTD is the promoter on 7 MahaRERA-registered projects, of which 7 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:
See every Marvel Realtors AND Developers LTD project & its RERA track record →
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026