MahaRERA Property Intelligence · Pune

PLATINUM PARK

P52100008065 · Man · promoter Saffron Properties And

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP52100008065
Registered on18 Aug 2017
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Saffron Properties And is the promoter of record on 21 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
A WING1G+1130 Dec 2020
B WING1G+1030 Dec 2020

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000022836202/03/2023Ankush Shrivastav vs M/s Saffron Properties and Schemesorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202430 Jun 2023Work completed upto 90 % final stage work will be completed in next 3 months and the documentation part needs further 2 months to receive cc for the project.
31 Dec 202430 Jun 2022REASON FOR DELAY IS DUE TO COVID 19 THATS WHY ITS GETTING LATE TO THE COMPLETION PROCESS. SO PLEASE ACCEPT OUR REQUEST AND MAKE CHANGES.
31 Dec 202431 Dec 2024The project is complete and the completion certificate or 179 out of 181 flats is already uploaded. form 4 along with this completion status is uploaded. this extension is required

Location, Land & Connectivity

Located at Man, man, Mulshi, Pune, 411057. Per the filed land record, the plot is bounded to the north by PART OF SURVEY NO 164-2, to the south by SURVEY NO 164, to the east by SHANTARAM PARKHI AND OTHERS and to the west by ANANDRAO PANDHARINATH THAKUR. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park2 km
Baner–Balewadi belt6 km
Pune Junction / city centre17 km
Pune Int'l Airport (Lohegaon)20 km
Magarpatta / Hadapsar IT22 km
Kharadi / EON IT Park23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wakad

Fusion Towers Phase III
possession by Jul 2026 · Rama Synergy Spaces
ANP Bizsquare
possession by Jul 2026 · Five Star Vighnesh Associates
Olive Orchard
possession by Jul 2026 · Anandtara Properties
Fairmont
possession by Aug 2026 · Krishna Icon Skyscraper LLP
Varad Residency
possession by Sep 2026 · Vilas Bhagaji Arekar
ANP Memento
possession by Sep 2026 · Five Star Construction Company

Major developers building in Wakad

Other RERA-registered projects in Pune

Platinum Park Phase I
declared completion Dec 2019 · Ranjeet Property Developers India Pvt. L
Platinum Park Phase II
possession by Dec 2026 · Ranjeet Property Developers India Pvt. L
Platinum Plaza
declared completion Dec 2025 · K C B Builders
Platinum Pride
declared completion Jun 2026 · Shree Mauli Developers
Platinum Square
declared completion Jun 2026 · Platinum Promoters
Platinum Square Phase 1
declared completion Dec 2017 · Vascon Engineers Ltd

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026