MahaRERA Property Intelligence · Pune

Prakalp Pride

P52100001299 · Pune · promoter Prakalp Infrabuild And

Certificate SignedDue 30 Jun 2022

Delivery & Registration

MahaRERA registrationP52100001299
Registered on27 Jul 2017
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Prakalp Infrabuild And is the promoter of record on 27 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Prakalp Pride1G+730 Jun 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202231 Dec 2021Project of Prakalp Pride is delayed due to following unavoidable circumstances. 1) Proposed date of completion was 30th June 2021. But since April 2021 lockdown was declared du
30 Jun 202230 Dec 2020Project of Prakalp Pride is delayed due to following unavoidable circumstances; Proof 1) As per POA/ DA no 12078/2014 dtd 19/12/2014, Land owners had agreed to give TDR & paid FSI.

Location, Land & Connectivity

Located at Pune, Mumbai Pune Highway, Haveli, Pune, 411045. Per the filed land record, the plot is bounded to the north by 105 Part , to the south by 104, to the east by 105 Part and 5 Are Plot and to the west by Road and remaining 105 Part. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Baner–Balewadi belt2 km
Hinjewadi Rajiv Gandhi IT Park4 km
Pune Junction / city centre12 km
Pune Int'l Airport (Lohegaon)16 km
Magarpatta / Hadapsar IT18 km
Kharadi / EON IT Park18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Baner

7 Business BAY
possession by Jul 2026 · Saaj Buildcon Private Limited
Maitreya
Not filing quarterly progress reports · possession by Jul 2026 · Vaibhav Shamrao Taro
Mercury
possession by Aug 2026 · SB Real Estate Private Limited
Aarambh
possession by Aug 2026 · ADI Realtors
Nancy Hillview A-1
possession by Aug 2026 · M/S Sarsan Aawishkar Properties
Truspace Platina
possession by Aug 2026 · Atharva Developments

Major developers building in Baner

Other RERA-registered projects in Pune

Prakash B Zone
declared completion Dec 2024 · Prakash Ventures
Prakash Gateway
declared completion May 2023 · Shreyas Ashokkumar Pagariya
Prakash Greens
declared completion Oct 2018 · Prakash Ventures
Prakash Nilay
declared completion Jan 2021 · Prakash Infracon
Prakash Residency
possession by Dec 2028 · Prakash Buildwell
Prakriti -C- Navyangan
declared completion Dec 2017 · Calyx Merlin Ventures LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026