K-RERA · the public record
Century Sports Village
Devanahalli · Prakruti Century Properties
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Jun 2018
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 20 Sep 2026
Inventory & scale
What this registration contains.
Filed categories, unchanged · K-RERA registration · read 20 Sep 2026
The whole registration
51.1registered acres
The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1250/303/PR/170918/000844
This project, on the record
The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.
On the register
Values as crawled from the official K-RERA record; context percentiles name their comparison population.
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Registered land area | 206,791 sqm | The land area attached to this K-RERA registration. |
| Open-parking field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Garage field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Project start date | 31-12-2015 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingNo litigation declared on this project's K-RERA filing.
4 of 23 compliance document slots are filed as Not Applicable; the remaining 19 slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
⚠ Registration validity has lapsed: originally due 30 Jun 2018, extended (Section 6 Extension) to 30 Jun 2019 — both dates have passed with no OC on file. The extension on file was granted on 22 Jul 2019 (K-RERA extension no. EX/PRM/KA/RERA/1250/303/PR/190722/000844) — it has been used, its deadline has also passed, and no further extension is recorded.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
K-RERA complaint orders (3 complaints against a project of this name on K-RERA's orders register)
| Parties | Relief sought | Disposal | Order date |
|---|---|---|---|
| Tuhin Sharma vs Century Sports Village | Refund of Rs.8,03,160/- ; 24% annual interest on the amount from the date of payment, 50,000/- for due diligence; 2,50,000/- for mental harassment, Litigation expenses. | AUTHORITY | 28/04/2026 |
| NIBEDITA PADHI & PRIYABRATA MOHAPATRA vs PRAKRUTI CENTURY PROPERTIES | Please help in getting the booking amount refund of 1 lakh back and take strict action against the builder as they have hidden the fact (case) in the RERA portal and share the document after booking. | AUTHORITY | 15/12/2022 |
| KIRAN KUMAR & SHWETHA K.R. vs M/S PRAKRUTI CENTURY PROPERTIES | Refund with Interest and penalty for the entire amount for almost 6 years and 3 months + Additional Compensation for the losses in appreciation of the property value | AUTHORITY | 04/08/2023 |
⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.
Complaints on this project's K-RERA page (3 complaints listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/191112/0004702 12-11-2019 | Plot not released for registration | Century Sports Village | DISPOSED AO |
| CMP/201219/0007288 19-12-2020 | Obligation to sell the property not met after full collecting the sale agreement amount and hiding litigation issues of the property | Century Sports Village | DISPOSED AUTHORITY BENCH4 |
| CMP/201229/0007343 29-12-2020 | The project land has litigation with forest department. I do not want to buy the land and want a complete refund of booking amount | Century Sports Village | DISPOSED AUTHORITY BENCH4 |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
Builder track record
RERA filingCentury Real Estate has 18 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Prakruti Century”) (average reported construction progress 59%). 10 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.
Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.
Financials & Construction Progress
Financial disclosures
RERA filing⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.
The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.
RERA 70% project account is on file: HDFC Richmond Road (IFSC HDFC0000523, a/c …4590). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Construction photo filings
RERA filingK-RERA has 1 project-photo upload.
These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.
Location & Connectivity
The nearest major job hub is ~22 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Kempegowda Int'l Airport | 4 km |
| Outer Ring Road / Manyata | 22 km |
| MG Road / city centre | 29 km |
| Whitefield IT hub | 29 km |
| Bellandur–Marathahalli belt | 32 km |
| Electronic City | 43 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.