IVORY PHASE 2 AT BRIGADE ORCHARDS

Devanahalli · BCV Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

83%construction reportedQ1 2026 filing
0units not bookedof 487 · Q1 2026 filing
31 Dec 2027declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

1 BHK + 1 TOILET + STUDY
66
3 BHK + 3 TOILET
60
1 BHK + 1 TOILET + STUDY
30
1 BHK + 1 TOILET
30
2 BHK + 2 TOILET
56
3 BHK + 2 TOILET
129
STUDIO UNIT
3
1 BHK + 1 TOILET
14
2 BHK + 2 TOILET
84
3 BHK + 3 TOILET
13
2 BHK + 2 TOILET
2

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

3.5registered acres

139.4registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/303/PR/151223/006485

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2027
Land area14,134 sq m (3.5 acres)
Homes registered487
Tower/wing entries3
Unit mix96 × 1 BHK + 1 TOILET + STUDY, 73 × 3 BHK + 3 TOILET, 44 × 1 BHK + 1 TOILET, 142 × 2 BHK + 2 TOILET, 129 × 3 BHK + 2 TOILET, 3 × STUDIO UNIT

In context

Density139.4 homes per acre
Density in context93rd percentile of 72 Devanahalli projects (median 68.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units487Total inventory registered with K-RERA.
Official carpet area28,758 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area54,989 sqmUseful scale context when comparing density and project cost.
Registered land area14,134 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.34Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)415Separate filed counts; these categories may overlap and are not added together.
Covered-parking field353Separate filed counts; these categories may overlap and are not added together.
Open-parking field74Separate filed counts; these categories may overlap and are not added together.
Garage field427Separate filed counts; these categories may overlap and are not added together.
Approved plan numberSTRRPA/TP/CC/77/2021-22Use this to match the sanctioned drawing set shown by the builder.
Plan approval date26-08-2021
Project start date05-12-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
1 BHK + 1 TOILET + STUDY6614%42 sqm
3 BHK + 3 TOILET6012%83 sqm
1 BHK + 1 TOILET + STUDY306%43 sqm
1 BHK + 1 TOILET306%34 sqm
2 BHK + 2 TOILET5611%58 sqm
3 BHK + 2 TOILET12926%69 sqm
STUDIO UNIT31%28 sqm
1 BHK + 1 TOILET143%31 sqm
2 BHK + 2 TOILET8417%58 sqm
3 BHK + 3 TOILET133%80 sqm
2 BHK + 2 TOILET20%51 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
J141437144.85 m
K1417017044.85 m
L1417417444.85 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 487 official flat/unit rows, matching the 487 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK20269.4-82.5 sqm33.4-39.5 sqm202
2 BHK14251.4-58.5 sqm25.9-28.0 sqm142
1 BHK14031.0-42.5 sqm17.6-22.8 sqm71 (69 with 0)
NA328.5 sqm14.9 sqm0 (3 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
L17451.4-82.5 sqm25.9-39.5 sqm174
K17051.4-82.5 sqm25.9-39.5 sqm170
J14328.5-42.5 sqm14.9-22.8 sqm71 (72 with 0)
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
J 0033J01 BHK33.7 sqm18.4 sqm1
J 0034J01 BHK33.7 sqm18.4 sqm1
J 0035J01 BHK42.5 sqm22.8 sqm1
J 0036J01 BHK42.5 sqm22.8 sqm1
J 0037J01 BHK31.0 sqm17.6 sqm1
J 0038J0NA28.5 sqm14.9 sqm0

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

13 of 45 compliance document slots are filed as Not Applicable; the remaining 32 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (4 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/201113/0007055
13-11-2020
deviation in the construction planJuniper at Brigade Orchards (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/210120/0007451
20-01-2021
Complaint for Refund with CompensationJuniper at Brigade Orchards (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/210308/0007763
08-03-2021
Registration without flat demonstrationJuniper at Brigade Orchards (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/220524/0009514
24-05-2022
Delayed Possession and pending facilities yet to be completedJuniper at Brigade Orchards (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

3 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved30-08-2011Brigade Orchards - Central Ground water Authority-30-8-2011.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved30-04-2014Brigade Orchards - KSPCB 30-4-14.pdf
KSPCB- MOEF (Above 50 Acres)Approved02-04-2014Brigade Orchards - MOF -2-4-2014.pdf
KPTCL- BESCOMApproved27-12-2012Brigade Orchards - BESCOM NOC 27-12-2022.pdf
Fire and SafetyApproved05-06-2015Ivory at Brigade Orchards - Fire NOC revised 2.pdf
Airport Authority of IndiaApproved30-03-2021Brigade Orchards - AAI NOC 03-03-2021.pdf
BSNL/Telecommunication DepartmentApproved06-11-2015Brigade Orchards - AAI NOC 03-03-2021.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantR. Srinivasan28982000Bengaluru Urban, Karnataka - 560003
EngineerDinesha ShettyBCC/BL-3.6/SE-166/2014-20152007Bengaluru Urban, Karnataka - 560003
ArchitectPAUL MANOHARAN MOSESCA/85/094701996Bengaluru Urban, Karnataka - 560001
ContractorBrigade Inhouse Construction-1986Bengaluru Urban, Karnataka - 560055

Builder track record

RERA filing

Bcv Developers has 9 other K-RERA-registered projects in our records (average reported construction progress 62%). 5 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹8.81 Cr collected from buyers, ₹5.03 Cr withdrawn from the project's escrow account.

Construction progress68% → 83% (+15 pts)
Units sold/booked as registered487/487 (100%)
Buyer collections in available QPRs₹33.48 Cr
Escrow withdrawals in available QPRs₹22.39 Cr (0.67x collections)
  • 100% of registered units are shown as sold/booked, but no completion certificate is on file yet.
  • Construction progress moved from 68% to 83% across the filed QPR window.
  • The builder has drawn 0.67x of buyer collections from escrow (about 67% of the ₹33 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹38.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Axis Bank Malleshwaram IFSC Code : UTIB0000227 Pin Code : 560003. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~24 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kempegowda Int'l Airport5 km
Outer Ring Road / Manyata24 km
Whitefield IT hub30 km
MG Road / city centre32 km
Bellandur–Marathahalli belt34 km
Electronic City44 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Bcv Developers. View Bcv Developers's full track record →
Bcv Developers has 10 projects registered in Bangalore, 2 completed.
1 complaints on the K-RERA register against Bcv Developers in Bangalore.

Other projects by this builder in Bangalore

Ebony At Brigade Orchards
On track · 36% built · 89% sold
Fairmont At Brigade Orchards
On track · 99% built · 100% sold
Goldspire At Brigade Orchards
No filings
Ivory Phase 1 At Brigade Orchards
On track · 100% built · 99% sold
Juniper At Brigade Orchards
No filings
Kino @ Brigade Orchards
No filings

Other RERA-registered projects in Devanahalli

Under The Sun – Luxury Villa Lifestyle By Fortius
Construction Of 423 Houses In Vijayappura & Devan

Major developers building in Devanahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Ivory Phase 2 AT Brigade Orchards?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026