RERA Property Intelligence Report · Preview

Ozone Urbana

Ozone Urbana Infra Developers · · K-RERA PRM/KA/RERA/1250/303/PR/171019/000287

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
3
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

1,893
Registered units
₹1080.0 Cr
Est. construction cost
Units profiled
27
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units1,893Total inventory registered with K-RERA.
Official carpet area50,246 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area124,521 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~2.12Sanctioned floor-area ratio (≈263,809 sqm sanctioned FAR area ÷ 124,521 sqm land) — higher means a denser vertical build.
Registered towers/wings7Official tower/wing count in the K-RERA detail page.
Parking disclosed2,030 total (159 open) — 1.07 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date01-10-2013

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Flats468100%50,246 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Alcove35293-
BELVEDERE384162-
IRENE7147139-
Aqua27232232-
Avenue121,0341,060-
Pavillion7320320-
Aura42424-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 1,893 official flat/unit rows, matching the 1,893 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK1,1761.0-166.5 sqm34.3-112.6 sqm1,176
2BHK4601.0-98.5 sqm27.8-75.1 sqm460
4BHK1361.0-207.9 sqm56.2-128.3 sqm136
2 BHK7760.3-68.9 sqm35.2-39.6 sqm77
1 BHK3540.1-40.2 sqm23.6-23.8 sqm35
NA80.0 sqm0.0 sqm7 (1 with 0)
3 BHK193.8 sqm38.8 sqm1

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Pavillion1,03478.1-207.9 sqm30.8-84.9 sqm1,034
Aura32078.7-107.4 sqm49.8-76.0 sqm320
Avenue2321.0 sqm27.8-61.2 sqm232
BELVEDERE1470.0-77.9 sqm0.0-44.5 sqm147
Aqua2840.0-158.2 sqm0.0-112.6 sqm83 (1 with 0)
Alcove5295.5-161.2 sqm73.3-122.0 sqm52
IRENE24126.1-154.1 sqm104.5-128.3 sqm24
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-G01Alcove02BHK95.5 sqm73.8 sqm1
A-G02Alcove03BHK123.3 sqm90.8 sqm1
A-G03Alcove03BHK143.7 sqm112.0 sqm1
B-G01Alcove02BHK95.5 sqm73.8 sqm1
B-G02Alcove03BHK130.8 sqm101.6 sqm1
B-G03Alcove03BHK138.8 sqm104.0 sqm1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~974 sqft — mid-format homes (2–3BHK territory), not compact stock. This is a large, multi-tower township — 1893 homes across 7 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 2,030 parking spaces for 1,893 homes (~1.1 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~53 sqm per home; across all 1,893 homes that is ~80% of the plot — a healthy sign: buyers collectively hold close to all the land. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

1 of 22 compliance document slots are filed as Not Applicable; the remaining 21 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2022, extended (Covid Extension) to 30 Sep 2023 — both dates have passed with no OC on file. An extension application filed on 07 Sep 2023 is pending with K-RERA — until it is approved, the registration stands lapsed.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (383 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
DR HARISH RAWAT vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDFULL CANCELLATION REFUND WITH INTERESTAUTHORITY30/12/2022
GAGAN CHATURVEDI vs Ozone Urbana Infra Developers Private LimitedPayment of Amount due as per buyback agreement & closure of loan by BuilderAUTHORITY30/11/2024
GAGAN CHATURVEDI vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDPayment of Amount due as per buyback agreement & closure of loan by BuilderAUTHORITY30/11/2024
Mrs Neha Verma Dugar & Saahil Dugar vs Ozone Urbana Infra Developers Pvt Ltd & anotherRefund of entire amount of Rs.10,88,495 with interest as per sec 18 of RERA Act, refund of PRE-EMI amounts paid, closure of loan, repay litigation fees incurred by the complainant & other reliefsAUTHORITY30/11/2024
Mr Phirojsha irani vs Ozone Urbana Infra Developers Private Limited & AnotherRefund of entire amount of Rs. 9,81,085 with interest,refund of loan amount to IHFL,refund of PRE-EMI amounts paid, closure of loan, repay entire litigation fees/charges incurred by CMP & other reliefAUTHORITY30/11/2024
Mr Bhavini Gautam Jhaveri & Akbarali Umidali Jairazbhoy vs Ozone Urbana Infra Developers Pvt Ltd & anotherRefund of entire amount of Rs Rs.6,68,532/- paid along with interest as per section 18 of RERA, refund the entire loan amount to IHFL, closure of loan account, repay litigation fees & other reliefsAUTHORITY30/11/2024
Mr Tahir Bagasrawala & Iqbal Bagasrawala vs Ozone Urbana Infra Developers Pvt Ltd & anotherRefund of entire amount of Rs. 11,54,958/- with interest, refund of loan amount to IHFL, refund of pre-emi’s amounts paid, closure of loan account, repay entire litigation fee& other reliefsAUTHORITY30/11/2024
Yogesh Vijj vs M/s.Ozone Urbana Infra Developers Pvt Ltd and othersCancellation of agreements, refund, closure of bank account, payment of PEMIs and and outstaing chargesAUTHORITY30/09/2025
Pattabhi Sudindra vs M/s.Ozone Urbana Infra Developers Pvt Ltd and othersExit from Project, Refund of Amounts paid under Agreements, Payment of Pre-EMIs and other charges & penalties imposed, Closure of loan account with M/s. HDFC LimitedAUTHORITY30/09/2025
Ravindra N Shantagiri vs OZONE URBANA INFRA DEVELOPERS PVT LTDDelay penalty as per RERA Act and delivery of flatAUTHORITY30/09/2022
Shreeniwas Jadal vs OZONE URBANA INFRA DEVELOPERS PVT LTDI want developer to close/terminate my on going loan by paying off as per agreement.AUTHORITY30/09/2022
Supriya Bhat & Archana Bahulekar vs OZONE URBANA INFRA DEVELOPERS PVT LTDRecovery of invested monies, promised investment returns, promised compensation for delay, compensation for breach of contract, closure of Home Loan in its entirety (as per agreement)AUTHORITY30/09/2022
Vinod Kumar And Parul Chaudhary vs OZONE URBANA INFRA DEVELOPERS PVT LTDExist from this project with full refund along with Interest of 18%AUTHORITY30/06/2022
Mr Rajendra Bansal vs OZONE URBANA INFRA DEVELOPERS PVT LTDDelay Compensation of sum of Rs.62,16,480/- Plus compensation for further delay till handing over possession of the Apartment No.D 801. (Please refer to the Compliant for Additional reliefs prayed)AUTHORITY30/06/2022
Mrs Begum Rafiunnisa vs OZONE URBANA INFRA DEVELOPERS PVT LTDRefund of entire amount received by builder with interest as per RERA & clear bank loan amount taken in the name of complainants as per Agreement termsAUTHORITY29/09/2022
Tom Cyriac vs Ozone Urbana Infra Developers Pvt LtdHence, the purchaser wishes to cancel the agreement to sale and the construction agreement dated 13.11.2015 and return the total amount disbursed by the purchaser to the promoter along with interest.AUTHORITY29/08/2022
Harjit S Singh vs Ozone Urbana Infra Developers Pvt LtdCompensation for delay and related losses sufferedAUTHORITY29/08/2022
Prashant Kapur vs Ozone Urbana Infra Developers Pvt LtdFULL CANCELLATION AND REFUND WITH INTEREST AND CLOSURE OF LOAN WITH BANKAUTHORITY29/08/2022
K Amit & MRS.P. SAVITHRI vs OZONE URBANA INFRA DEVELOPERS PVT LTDRefund Paid capital, Interest serviced, Rent paid during delay, legal fees and compensation for mental agonyAUTHORITY29/08/2022
Aishwarya Jayanth vs OZONE URBANA INFRA DEVELOPERS PVT LTDRefund of deposit plus an interest of 18% per annum, calculated from the date of payment of each installment.AUTHORITY29/08/2022
Hussain Chittaliya vs M/S.OZONE URBANARefund the advance consideration paid by the Complainant as pre deposit, EMI/PRE-EMI and other charges along with the interest and absolve the Complainant from the loan liabilityAUTHORITY29/06/2026
Anjali Jayant Bhaisare vs M/S.OZONE URBANARefund of the amount with interest along with other appropriate reliefsAUTHORITY29/06/2026
WILFRED ARAMBHAN vs M/S.OZONE URBANARefund with interest and closure of loanAUTHORITY29/06/2026
Amol Vinod Chinchpurkar vs M/S.OZONE URBANARefund of my contribution and closure of loan as per buyback and tripartite agreementAUTHORITY29/06/2026
ANISHA ANAND vs M/S.OZONE URBANARefund with interestAUTHORITY29/06/2026
Advanced Engineering Services Private Limited vs M/S.OZONE URBANARefund with interestAUTHORITY29/06/2026
Amit Kaul vs OZONE URBANA INFRA DEVELOPERS PVT LTDFinancial compensation:a. Loss of rent b. InterestAUTHORITY28/09/2022
ARUN KESAVARAJ vs OZONE URBANA INFRA DEVELOPERS PVT LTDCompensation for depression caused and interest reAUTHORITY28/09/2022
Prakash Kumar Mohapatra vs OZONE URBANA INFRA DEVELOPERS PVT LTDOccupancy certificate, khata transfer and appartment association formationAUTHORITY28/09/2022
Shaila Manohar vs OZONE URBANA INFRA DEVELOPERS PVT LTDSeeking entire Refund and compensation from the builderAUTHORITY28/09/2022
PRATEEK SABHARWAL vs OZONE URBANA INFRA DEVELOPERS PVT LTDOZONE HAS BEEN RAISING AN INVOICE FOR MAINTENANCE EVERY QUARTER SINCE APR 2020 AND ITS NOT PAYABLE SINCE OC NOT RECEIVED . MAINTENANCE TO BE PAYABLE ONLY FROM DATE OF OC RECEIPT AND KHATA TRANSFERAUTHORITY28/09/2022
PRATEEK SABHARWAL vs OZONE URBANA INFRA DEVELOPERS PVT LTDBUILDER HAS BEEN SENDING MAINTENACE BILLS SINCE MARCH 2020 AND IT DOES NOT APPLY AS OC IS NOT PROVIDED AND KHATA TRANSFER NOT DONE HENCE NO MAINTENANCE PAYABLEAUTHORITY28/09/2022
ROOPASHRI SUNDARESH vs OZONE URBANA INFRA DEVELOPERS PVT LTDEither refund of full money paid towards the apartment (Rs.73,26,376/- plus reasonable interest for 4 year delay) or speedy provision of occupancy certificate and BESCOM connection to enable khata traAUTHORITY28/08/2024
Sandeep Kumar Sharma, Ved Prakash Sharma & Ashima Tuli Sharma vs Ozone Urbana Infra Developers Private LimitedRefund, Breach of Agreement, Compensation, Exit from Project, Payment of Promised Return Value, Payment of Outstanding Loan AmountAUTHORITY27/11/2023
Sandeep Kumar Sharma, Ved Prakash Sharma & Ashima Tuli Sharma vs Ozone Urbana Infra Developers Private LimitedExit from Project, Payment of Outstanding Loan Dues, Payment of Committed Profit Value, Compensation, Costs of ProceedingsAUTHORITY27/11/2023
Sadhasivam Palani & Anusha Sadhasivam vs Ozone Urbana Infra Developers Private Limitedfull Refund with interest and compensationAUTHORITY27/11/2023
ABHISHEK MAKKAR vs OZONE URBANA INFRA DEVELOPERS PVT LTD1) Immediate possession of the Property without any further delay or compensation of rent from the deliver date 2) EMI to be borne by the builder as they had promised to pay until possessionAUTHORITY27/09/2022
G KARTHIKEYAN vs OZONE URBANA INFRA DEVELOPERS PVT LTDSeeking cancellation of Flats and for the refund of money along with the interestAUTHORITY27/09/2022
Anish Issac vs OZONE URBANA INFRA DEVELOPERS PVT LTDTo cancel the Flat booking, Refund Rs. 9,92,525/- along with returns of 100%, To refund Rs. 8,01,693/- paid towards the PEMI along with 8% interest Pa.,AUTHORITY27/09/2022
Priyesh Sinha vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDExecution of cancellation of Agreement for Sale, refund of amount paid, payment of committed profit value, compensation, payment of all EMIs, closure of loan account, costs of proceedingsAUTHORITY27/08/2024
RAJESH AGARWAL vs M/S.OZONE URBANA AND OTHERSCOMPLETE AMOUNT PAID BY US ALONG WITH INTERESTAUTHORITY27/04/2026
MR.VIKAS JAIN AND ANOTHER vs M/S.OZONE URBANA INFRA DEVELOPERS AND OTHERSRefund with interestAUTHORITY27/03/2025
MR VIKAS JAIN AND ANOTHER vs M/S.OZONE URBANA INFRA DEVELOPERSRefund with interestAUTHORITY27/03/2025
Prashant Tripathi And Tripti Tripathi vs Ozone Urbana Infra Developers Pvt LtdBuilder has to pay the interest of of flat value along with compensation for amenties and delay penalties .AUTHORITY26/10/2023
Ashish Jaiswal vs OZONE URBANA INFRA DEVELOPERS PVT LTDPlease get refund all my payments along with interest from Builder/Promoter/Developer (Ozone Urbana Infra Developers Pvt Ltd.) and close all my loan responsibilities with HDFC Ltd.AUTHORITY26/09/2022
Ashish Jaiswal vs OZONE URBANA INFRA DEVELOPERS PVT LTDPlease get refund all my payments along with interest from Builder/Promoter/Developer (Ozone Urbana Infra Developers Pvt Ltd.) and close all my loan responsibilities with HDFC Ltd.AUTHORITY26/09/2022
Ashish Jaiswal vs OZONE URBANA INFRA DEVELOPERS PVT LTDPlease get refund all my payments along with interest from Builder/Promoter/Developer (Ozone Urbana Infra Developers Pvt Ltd.) and close all my loan responsibilities with HDFC Ltd.AUTHORITY26/09/2022
JEETENDRA BHANU KUMAR VERMA vs OZONE URBANA INFRA DEVELOPERS PVT LTDRefund of entire amount paid to Ozone with interest component till the payment is madeAUTHORITY26/09/2022
Dr Lakshmi Kannan vs OZONE URBANA INFRA DEVELOPERS PVT LTDComplete refund of all payments made plus interest accrued and exit from the projectAUTHORITY26/09/2022
Pradeep Kumar Sundar Shetty vs OZONE URBANA INFRA DEVELOERS PRIVATE LIMITEDNeed RERA’s intervention to hold the builder accountable to Buyback and pay me assured returns along with Penalty for the delay.AUTHORITY26/08/2024
Bupur Ramesh vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDFull refund with interestAUTHORITY26/08/2024
Tripti Shivhare vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDDirect Respondent Developer to Refund the entire sale consideration with rera prescribed rate of interestAUTHORITY26/08/2024
Puravoor Sanjeev Unnikrishna Panicker vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund of invested amount with promised return and closure of loan in my nameAUTHORITY26/07/2023
G Y Rajashekar vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDI am seeking full refund of all the PEMI’s paid by me till date and request RERA to provide a stay order so I can stop paying any further PEMI's until occupancy.AUTHORITY26/07/2023
Rakesh Agarwal vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDFull refund of the amount paid and the cancellation of the booking and closure of the loan.AUTHORITY26/07/2023
Moiz Abdulhusain Tankiwala & TASNEEM MOIZ TANKIWALA vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund of invested amount with promised returns and closure of loanAUTHORITY25/11/2024
SWETHA RAMDAS vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITED & 2 OTHERSThe complainant claims full refund of all payments made, along with interest, compensation and litigation costs, and any other relief deemed appropriate under the circumstances.AUTHORITY25/11/2024
PRIYANKA ANAND vs M/S.OZONE URBANARefund with interestAUTHORITY25/06/2026
Narayan Janardan vs M/S.OZONE URBANARefund of own contribution and EMI paid interest and Closure of loan with no liability on ComplainantAUTHORITY25/06/2026
PRESIDENT OZONE URBANA BUYERS WELFARE ASSOCIATION vs Ozone Urbana Infra Developers Pvt LtdCOMPENSATION OF RS2500000/- (25LAC PER INVESTOR) AS PER LIST ATTACHED TO BE ADDED TO RERA ORDERS / RRC WITH INTEREST AS PER RERA ORDERSAUTHORITY25/06/2025
Shiraz Kunnummale Purayil vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDDirecting the Respondent Builder to refund the sum of Rs. 52,49,876/-(Rupees Fifty Two Lakhs Forty Nine Thousand Eight Hundred And Seventy Six Only) along with other Monies paid by the Complainant.AUTHORITY25/05/2023
SRINIVASAN NATARAJAN vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund with interest and compensationAUTHORITY25/05/2023
Gourvendu Saxena vs Ozone Urbana Infra Developers Pvt LtdPenalty on Ozone and its managementAUTHORITY25/03/2026
Jignesh Rajnikant Sejpal & Asha Jignesh Sejpal vs Ozone Urbana Infra Developers Private LimitedDelay period interest as well a fixed timeline to complete the handover with OCAUTHORITY25/03/2024
Mr Hampesh Manjappa Hampanna vs M/S.OZONE URBANArefund and compensation of amount , Cancellation of agreement and Closure of Loan AccountAUTHORITY24/06/2026
Arman Hayat vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund along with exit.AUTHORITY24/05/2023
Nitin Sambyal vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund with Interest and compensationAUTHORITY24/05/2023
Swarnalata Ajay Kotian vs M/S.OZONE URBANA AND OTHERSRefund with interest along with other appropriate reliefsAUTHORITY24/02/2026
MR BHAVESH DINESH VIRA AND ANOTHER vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTDRefund of with interest of own contribution, PEMIs paid and Bank LoanAUTHORITY24/01/2025
Rajesh Sanna Reddy vs OZONE URBANARefund with interestAUTHORITY23/09/2025
Rajni Parshotam Das vs OZONE URBANA INFRA DEVELOPERSThe complainants seek immediate possession of duly completed apartment with delay period interest and other entitled reliefs.AUTHORITY23/09/2025
Srinagesh Vitthanala vs OZONE URBANArefund amount with interest as per section 19 of RERA ActAUTHORITY23/09/2025
SONAM RAHUL BUDHWANI vs OZONE URBANAI. To direct the Respondent to refund the amount complete amount paid by the Complainants along with interest at prescribed rates from the date of each payment till its actual realisation.AUTHORITY23/09/2025
Sitarama Raju Alluri vs M/s.Ozone Urbana and othersRefund with interestAUTHORITY23/09/2025
Parth Agrahari vs M/s.Ozone Urbana and othersRefund with InterestAUTHORITY23/09/2025
Adnan Khan vs M/s.Ozone Urbana and othersRefund with interestAUTHORITY23/09/2025
Shankar Ganiger vs Ozone Urbana Infra Developers Private LimitedRefund with interestAUTHORITY23/07/2024
Ankit Khare vs M/S.OZONE URBANARefund with interest and loan closureAUTHORITY23/06/2026
Kapil Khargonkar vs M/S.OZONE URBANA AND OTHERSWherefore, the Applicant respectfully prays that this Hon’ble Authority may be pleased to allow the instant complaint and award: a.Execution of cancellation of the Agreement of Sale dated 09.02.2021.AUTHORITY23/03/2026
Vaibhav Mohatta vs M/S.OZONE URBANA AND OTHERSa.Cancellation of the Agreement of Sale dated 29.11.2016: b.Refund of the entire amount paid to the Respondents till date by the Complainant and return on the same at 11% rate of interest from the duAUTHORITY23/03/2026
MOHAMMED AZIZUDDIN AZIMUDDIN vs M/S.OZONE URBANA INFRARefund with interest and closure of loanAUTHORITY23/02/2026
MR GYANESHWAR JADAL AND ANOTHER vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTD.Closure of loan and interestAUTHORITY23/01/2025
Ashish Thukral & Anuja Thukral vs M/s Ozone Urbana Infra Developers Private LimitedRefund of full amount with delay penaltyAUTHORITY22/12/2023
A HANUMANTHA CHAR vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund with interestAUTHORITY22/11/2024
Triloki Nath Challu vs OZONE URBANA INFRA DEVELOPERSRefund of full amount with interestAUTHORITY22/09/2023
MR SHAHJAHAN SHAHUL HAMEED M N vs OZONE INFRA DEVELOPERS PRIVATE LIMITED & OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDDirect Developer 1.Refund amount paid by complainant towards sale consideration with interest 2.Pay loan outstanding amount directly to Bank 3.Pay Complainant all Pre-EMI/EMIs paid to Bank till date.AUTHORITY22/08/2024
Sunil Kumar KV vs Ozone Urbana Infra Developers Private LImitedREFUND WITH INTERESTAUTHORITY22/08/2024
RAJESH VIJAYRAO BORIKAR & LAXMI RAJESH BORIKAR vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDSeek Delay Period Interest on the entire amount paidAUTHORITY22/08/2024
Vijeth Hegde vs Ozone Infra Developers Private LimitedRefund the entire Adavance Sale consideration amount of Rs 58,26,902/- along with 18% interest per year payable by Respondent to the Complainants in toto an amount of Rs 2 crore payable by respondentAUTHORITY22/06/2026
ADITYA RANJAN SAMANTARA vs M/S.OZONE URBANARefund of entire amount with interest & costs and other appropriate reliefsAUTHORITY22/06/2026
Amit Kaul vs M/S.OZONE URBANACANCELLATION, FULL REFUND OF AMOUNT PAID (INCL ALL PEMI/EMI PAID BY THE BUYER TILL DATE)ALONG WITH RERA PRESCRIPED INTEREST, PAYMENT OF OUTSTANDING LOAN AMOUNT, DELAY PERIOD INTEREST, COMPENSATIONAUTHORITY22/06/2026
Sanath Kumar N vs M/S.OZONE URBANASeeks delay period interest, costs and other appropriate reliefsAUTHORITY22/06/2026
Brijesh Ramdey Yadav vs OZONE URBANARefund of entire amount with interest & costs and other appropriate reliefsAUTHORITY22/06/2026
Sirsimth Meer Ashraf Ali vs M/S.OZONE URBANARefund with interest with other appropriate reliefsAUTHORITY22/06/2026
Ganeshan Venkateshwaran vs Ozone Infra Developers Private Limitedi) to refund the complete amount paid by the Complainant i.e., Rs. 7,13,023/- a/e interest ii) refund of the PEMIs paid by the Complainant i.e., Rs. 36,37,094/- a/w interest iii) compensationAUTHORITY22/06/2026
C A BHEEMA RAO vs Ozone Urbana Infra Developers Pvt LtdRefund of Amount paid with interest.AUTHORITY22/06/2026
Shilpa Srinivasan vs M/S.OZONE RBANARefund of amount paid with interest as per section 19 of RERA ActAUTHORITY22/06/2026
Amandeep Singh Longia vs M/S.OZONE URBANARefund with interest and closure of loan and violations of RERA ActAUTHORITY22/06/2026
Mustaqeem Sahib vs m/s.OZONE URBANA1. Direct the builder (Ozone Group) to immediately pay all pending EMIs to UCO Bank under the agreed subvention scheme. 2. Direct the builder to settle the outstanding loan amount with UCO Bank or coAUTHORITY22/06/2026
ERROL JOHN NORONHA vs OZONE URBAN INFRA DEVELOPERS PVT LTD.,REQUEST RERA AUTHORITY TO USE ITS AUTHORITY AS PUBLISHED ON RERA WEBSITE Enforcement of Judgments / Orders Passed by Appellate Tribunal As contemplated under Section 57 of the RERA Act and Rule 26AUTHORITY22/04/2025
OZONE URBANA BUYERS WELFARE ASSOCIATION vs OZONE URBANA INFRA DEVELOPERS PVT LTDIMMIDIATE REVOKE ALL LICENSING AND SEIZE ALL OZONE GROUP AND OZONE URBANA BANK ACCOUNTS WITH IMMIDIATE EFFECT IF NOT ABLE TO PRODUCE DOCUMENTATIONAUTHORITY22/04/2025
PRESIDENT OZONE URBANA BUYERS WELFARE ASSOCIATION vs OZONE URBANA INFRA DEVELOPERS PVT LTD.,FOLLOW THE RERA ACT AND PUNISH MR SATYAMOORTHY VASUDEVAN AND FAMILY AS PER RERA LAW ADVERTISED ON THE KARNATAKA RERA WEBSITE AND RULES AND REGULATIONSAUTHORITY22/04/2025
K M A Ayush vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTD & ANOTHERRefund with interestAUTHORITY22/04/2025
Mohamed Wajid Basha & Amreen Sultana vs Ozone Urbana Infra Developers Private LimitedRefund with interest and PEMI refundAUTHORITY22/04/2024
Ajitkumar Nair & Neesha Ajit Nair vs Ozone Urbana Infra Developers Private LimitedRefund with interest and cancellation of unitAUTHORITY22/04/2024
PRASANJEET GHOSH vs Ozone Urbana Infra Developers Private LimitedNeed Refund of money paid with interest.AUTHORITY22/04/2024
RADHAKRISHNA SHIBU vs M/S.OZONE URBANA AND OTHERSRefund the amount paid by the complainants including Pre-EMIs paid to bank with interest & Direct the Respondents to clear the loan outstanding.AUTHORITY21/10/2025
Vinayak V Kamath vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDCancel the apartment and Refund the amount paid by me to bank and Ozone along with application interest charges and compensationAUTHORITY21/09/2023
Mahesh Lingappa vs OZONE URBANA INFRA DEVELOPERS PVT LTDExit from project with full refund of own contribution and PEMI with interest and discharge of total bank loanAUTHORITY21/09/2022
TR Deepak & R Jayashree vs Ozone Urbana Infra Developers Private LimitedRefund with interest + Closure of loanAUTHORITY21/07/2024
Yogesh Vijayakumar vs OZONE URBANA INFRA DEVELOPERSCancellation of Unit and Refund of amounts due to me with interestAUTHORITY21/05/2025
Vijay Kumar Thakur vs M/S.OZONE URBANARefund Rs. 36,61,000/- with interest as per Section 18(1) of the Real Estate (Regulation and Development) Act, 2016 and duly compensate the Complainants as per Section 18(3)AUTHORITY21/04/2026
Rajagopal Shankar vs M/S.OZONE URBANA AND OTHERSRefund with interestAUTHORITY21/04/2026
Muneer Ponna Valappil & Najaha Hassan vs M/s Ozone Urbana Infra Developers Private LimitedTo direct the Respondent to repay a sum of Rs.54,35,000/- and Rs.1,00,000/- paid by the Applicant along with 12% interest per annum.AUTHORITY21/03/2024
DR KISHORE KUMAR BAHL vs M/S. OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDOnly 53% of the project work has been completed. Hence REFUND the entire amount paid by the complainant and permit to EXIT from the project.AUTHORITY20/12/2023
DR KISHORE KUMAR BAHL vs M/S OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDREFUND the entire amount paid by the complainant and permit to EXIT from the project.AUTHORITY20/12/2023
DR KISHORE KUMAR BAHL vs M/S OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDREFUND the entire amount paid by the complainant and permit to EXIT from the projectAUTHORITY20/12/2023
Dr Kishore Kumar Bahl vs M/S OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDDirect the Respondents to Refund the amount along with Compensation and interestAUTHORITY20/12/2023
Anil Kumar I vs OZONE URBANA INFRA DEVELOPERS PVT LTDTo grant the Complainant a sum of Rs 30,00,000/- (Thirty Lakhs Only) from the Respondent towards delay compensation and damages caused to the Complainant.AUTHORITY20/12/2022
Naveen Kumar DT vs OZONE URBANA INFRA DEVELOPERS PVT LTDComplete Refund of amount paid to builder as well as Pre EMI along with interest, and clear bank loan and liability associated with the property.AUTHORITY20/10/2022
Naresh Kumar Vijay vs OZONE URBANA INFRA DEVELOPERS PVT LTDeither handover said unit asap OR full refund of amount along with InterestAUTHORITY20/10/2022
SRIRAM SUBRAMANIAM VAIDYANATHAN & PRATHIBHA HARIHARA SUBRAMANIAN vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund of entire amount along with interest and payment of loan to BankAUTHORITY20/05/2024
Ravi Swaminathan vs M/s Ozone Urbana Infra Developers Private LimitedRefund of amount paid, interest on amount paid, interest on bank loans, compensation, costs of proceedingsAUTHORITY20/03/2024
Govindu Dwarakabhamidipati vs Ozone Urbana Infra Developers Private LimitedRefund of amount with interest and closure of loanAUTHORITY20/03/2024
Arjun SB vs M/s Ozone Urbana Infra Developers Private Limitedunit cancellation with refund of bank loan , booking amount ,PEMI interest payment made along with interestAUTHORITY19/12/2023
Bharath Kumar Reddy & Harshini Chintapalli vs M/s Ozone Urbana Infra Developers Private LimitedRefund of amount paid with interestAUTHORITY19/12/2023
Mukesh V Foflia & Bharati M Foflia vs M/s Ozone Urbana Infra Developers Private LimitedRefund of entire amount paid by Complainant until date, i.e., Rs. 67,90,009/-, along with delay compensation, as per Section 18 of the Real Estate (Regulation and Development) Act, 2016.AUTHORITY19/12/2023
SUNIT ARUNKUMAR JAIN & KOYEL BHATTACHARYA vs M/S OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund with interestAUTHORITY19/12/2023
Aseem Mishra vs OZONE URBANA INFRARefund with interest and closure of loanAUTHORITY19/11/2025
PRASAD MOHANACHANDRAN & USHA MV vs Ozone Urbana Infra Developers Private LimitedRefund with InterestAUTHORITY19/11/2024
Pradip S Kothali vs OZONE URBANADelay Period InterestAUTHORITY19/09/2025
Santosh Amasi vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDComplete refund with interest and compensationAUTHORITY19/09/2023
Ekta Verma vs OZONE URBANA INFRA DEVELOPERS PVT LTD1) Ozone has to Fore-close the HDFC Home Loan a/c No 622452743; and 2) Ozone needs to re-imburse the outstanding Pre-emis till date along with accrued interest.AUTHORITY19/09/2022
Srinivas Murali & Mrs Chitra Srinivas vs OZONE URBANA INFRA DEVELOPERS PVT LTDFull refund of all moneys paid by me to the builder with bank rate of interest from Aug 2018, compensation of loss of rental from flat after Aug 2018.AUTHORITY19/08/2022
AZAM AZIZ & ALWIRA AZIZ vs M/S OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDExit from Project, Refund, Payment of Outstanding Dues to Bank, Closure of Loan Account, CompensationAUTHORITY19/03/2024
Kumaravel Kandasami vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund of the amount paid along with Pre-EMI I paid along with interest for the same and closure of the loanAUTHORITY19/03/2024
Shankarappa Chapparadahally Ramegowda vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund with interest and closure of bank loanAUTHORITY19/03/2024
Pravin Pandey & Chhaya Pandey vs Ozone Urbana Infra Developers Private LimitedRefund of principal amount + PEMI paid by me on behalf of the builder with interestAUTHORITY19/03/2024
Sanjeeva C & Deepika N vs Ozone Urbana Infra Developers Private LimitedNeed delayed compensation form the builder and fixed time line as to when the project will be completed.AUTHORITY19/03/2024
Shreeshail Shivanand Nidoni & Basamma Shreeshail Nidoni vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund with interest and closure of loanAUTHORITY19/03/2024
Arindam Deb vs OZONE URBANARefund of entire amount with interest & costs and other appropriate reliefsAUTHORITY18/11/2025
Sunil Clifford Sequeira vs OZONE URBANARefund of Amount with interest.AUTHORITY18/11/2025
Shambhu Roy vs OZONE URBANARefund with interest, costs, and any other reliefs as deemed appropriate.AUTHORITY18/11/2025
PURNAPURANSHU SEKHAR JENA vs OZONE URBANARefund with interest with other appropriate reliefs.AUTHORITY18/11/2025
Anirban Deb vs OZONE URBANARefund with interest with other appropriate reliefsAUTHORITY18/11/2025
Malarselvan Tamilmani & Jayapriya Malarselvan vs Ozone Urbana Infra Developers Private LimitedRefund and closure of loanAUTHORITY18/10/2024
Karthik Srinivasan & Sudha Karthik vs Ozone Urbana Infra Developers Private LimitedBreach of Buyback Agreement and failure to close the loanAUTHORITY18/10/2024
Karthik Srinivasan & Sudha Karthik vs Ozone Urbana Infra Developers Private LimitedClosure of Loan and RefundAUTHORITY18/10/2024
Sameer Kumar & Sakshi vs Ozone Urbana Infra Developers Private LimitedExit from Project, Compensation, Payment of pre-EMIs, Closure of loan accounts, Payment of Penalties imposed by M/s. HDFC Bank, Pay the costs for Singapore Loan, Costs of proceedingsAUTHORITY18/09/2024
ERROL JOHN NORONHA vs OZONE URBANA INFRA DEVELOPERS PVT LTDCancellation and Full Refund with Interest to HDFC BANK and to Errol John NoronhaAUTHORITY18/08/2022
SumitaVeda vs OZONE URBANA INFRA DEVELOPERS PVT LTDCompensation for delay and related losses suffered.AUTHORITY18/08/2022
RashmiLuniaBhura vs OZONE URBANA INFRA DEVELOPERS PVT LTDBuilder has to pay the interest of flat value along with compensation for amenities and delay penalties and need to give the covered parking what we have paid for.AUTHORITY18/08/2022
Aakruthi Raju vs M/S.,OZONE URBANA INFRA DEVELOPERS PVT LTD.refund amount including pre-emi paid and interest as per section 19 of RERA ActAUTHORITY18/06/2025
Narasimha Rao Bandla vs MS/OZONE URBANA INFRA DEVELOPERS PVT LTD.refund amount including pre-emi paid and interest as per section 19 of RERA ActAUTHORITY18/06/2025
OZONE URBANA BUYERS WELFARE ASSOCIATION vs Ozone Urbana Infra Developers Pvt LtdIF HON'BLE RERA AUTHORITY HAS THE POWERS TO REVOKE THE LICENSE OF THE DEVELOPER IF PROVED UNABLE TO FURNISH ALL DETAILS AS REQUESTED KINDLY REVOKE THE LICENSE IMMIDIATELYAUTHORITY18/03/2025
Ozone Urbana Buyers Welfare Association vs Ozone Urbana Infra Developers Pvt LtdSEIZE OZONE URBANA PROJECT , OZONE GROUP IS FLAUTING ALL COMPANY RULES AND CHALLENGES THE COURTS BY BREAKING EVERY LAW WITH EASE .DIRECT OZONE GROUP TO FURNISH AUDITED ACCOUNTS PENDING SINCE 2017AUTHORITY18/03/2025
PRESIDENT OZONE URBANA BUYERS WELFARE ASSOCIATION vs Ozone Urbana Infra Developers Pvt LtdFORENSIC AUDIT ON CONSTRUCTION QUALITY FOR COMPLETE PROJECT AND REVOKE THE REGISTRATION COMPLETELY AND ENSURE NO FURTHER SALES AND POOR CONSTRUCTION TO COMPLETE PROJECT ARE ALLOWEDAUTHORITY18/03/2025
PRESIDENT OZONE URBANA BUYERS WELFARE ASSOCIATION vs Ozone Urbana Infra Developers Pvt LtdREVOKE LICENSE, REGISTRATION , BLOCK ALL OZONE URBANA AND OZONE GROUP ACCOUNTS FOR FALSE MARKETING AND USING RERA REGISTERED MARKETING TO PROMOTE SALESAUTHORITY18/03/2025
OZONE URBANA BUYERS WELFARE ASSOCIATION vs Ozone Urbana Infra Developers Pvt LtdFREEZE BANK ACCOUNTS AND ASSETSAUTHORITY18/03/2025
OZONE URBANA BUYERS WELFARE ASSOCIATION vs Ozone Urbana Infra Developers Pvt LtdAS PER LAW NON BAILABLE WARRANT FOR ARREST FOR MR VASUDEVAN SATYAMOORTHY AND ALL DIRECTORS INVOLVED IN THE LARGE SCALE SCAM REFER MANTRI CASE AND AMRAPALI CASEAUTHORITY18/03/2025
Mohammed Akram vs M/S.OZONE URBANA INFRA DVELOPERS AND OTHERSRefund of amount and cancellation of sale deedAUTHORITY17/11/2025
Pavan Kumar & Preethika Priya vs M/s Ozone Urbana Infra Developers Private LimitedRefund along with exit from projectAUTHORITY17/10/2023
Shaheena Parveen Saudagar & Syed Moinuddin vs Ozone Urbana Infra Developers Private LimitedRefund of the amounts paid with interestAUTHORITY17/04/2024
MR YERMAL CHANDRASHEKAR AND ANOTHER vs MS/.OZONE URBANA INFRA DEVELOPERS PVT LTDRefund with interestAUTHORITY17/01/2025
MR ANUP GUJALWAR vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTDRefund of Own Contribution, Buyback Amount and Closure of LoanAUTHORITY17/01/2025
MR CYRIL MATHEWS ALEXANDER vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTDRefund of own contribution, buy back amount, PEMI's paid and loan closureAUTHORITY17/01/2025
MR CHANDRASHEKAR N BASAPPA vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTD.Refund with interest of own contribution, closure of loan and buyback amountAUTHORITY17/01/2025
MR NAYUB MASTHAN VALI AND ANOTHER vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTDI seek complete refund of the amount paid along with Pre_EMI I Have paid along with interest for the same.AUTHORITY17/01/2025
Nasir Ahmed Khazi vs M/S.OZONE URBANA INFRA AND OTHERSApartment Handover and Delay InterestAUTHORITY16/12/2025
Venkatesh G Iyer vs OZONE URBANA INFRA DEVELOPERS PVT LTDTo award Delay Compensation of Rs 30,00,000/- (Thirty Lakhs Only) for delay of 58 months in delivery of Possession over Ozone Urbana Pavillion Apartment K -203, a 3BHK Apartment having 1540 Square Ft.AUTHORITY16/12/2022
Amol Agrawal vs OZONE URBANA INFRA DEVELOPERS PVT LTDCompensation for delay and related losses sufferedAUTHORITY16/12/2022
JYOTHI MUTHAPPA vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDEarly delivery of the apartment with all the interest and the delayed compensation at the earliest.AUTHORITY16/12/2022
Shalini Nagaraj vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDEarly delivery of the apartment with all the interest and the delayed compensation at the earliest.AUTHORITY16/12/2022
Mamata Kumari Choudhary & Ashok Kumar Sahu vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDExit from the project with refund of full amount actually paid by us with fair interest( as per the No-dues certificate) +Return of all Regstration and sale deed charges +cancellation of sale deedAUTHORITY16/11/2023
Yogish T Gowda vs OZONE URBANA INFRA DEVELOPERS PVT LTDQuashing of Maintenance charges until all the amenities are made availableAUTHORITY16/11/2022
Pradeep Ashok Kumar vs M/S.OZONE URBANA INFRA DEVELOPERS AND ANOTHERrefund amount including pre-emi paid and interest as per section 19of RERA ActAUTHORITY16/09/2025
Prashant Awasthi vs M/S.OZONE URBANA INFRA DEVELOPERS AND OTHERSRefund of amount with interest as per section 19 of RERA Act along with Pre emi/emi which is paid to the bank against loanAUTHORITY16/09/2025
NEERAJ GUPTA vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTD AND ANOTHERDirect Developer to 1.Refund sale consideration. 2.Pay the loan outstanding amount directly to the bank. 3.Pay to the Complainant all Pre-EMI and EMIs paid till date to bankAUTHORITY16/08/2025
AMIT MISTRY vs OZONE URBANA INFRA DEVELOPERSRefund with interest and buyback amount closure of loanAUTHORITY16/08/2025
CHANDRASHEKAR SIDDASETTY CHIKKAKALBALU vs M/S.OZONE URBANA INFRA DEVELOPERSrespondent is liable to pay Rs. 29,81,704/- being the interest as on 30th January 2024 & respondent is further liable to pay interest of Rs. 67,766 /- @ 15% p.a for every month of further delayAUTHORITY16/08/2025
Amit Saha vs M/S.OZONE URBANA INFRA DEVELOPES PVT LTD AND OTHERSPleased to order the respondents to refund entire amount, along with EMI amount paid by the complainant and direct the respondents to repay the entire outstanding home loan amount and obtain an NOCAUTHORITY16/08/2025
Manoj Jain vs OZONE URBANArefund amount including pre-emi paid and interest as per section 19of RERA ActAUTHORITY16/08/2025
Dipak Chaudhuri vs OZONE URBANArefund of amount paid with interest as per section 19 of RERA ActAUTHORITY16/08/2025
ALPANA MALDE & ANJU MALDE vs OZONE URBANARefund of entire amount of Rs.10,64159 Paid with interest as per sec 18 of RERA Act, refund of PEMIs amounts paid, closure of loan, repay litigation fees incurred by the Complainants & other reliefs.AUTHORITY16/08/2025
Srinagesh Vitthanala vs SRINAGESH VITTHANALArefund amount with interest as per section 19 of RERA ActAUTHORITY16/08/2025
Jagdish Jivanlal Wani vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTDThe complainant seeks duly completed apartment with delay period interest and other entitled reliefsAUTHORITY16/08/2025
Arindam Deb vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTD AND OTHERSRefund of entire amount with interest & costs and other appropriate reliefsAUTHORITY16/08/2025
Subhashree Saha vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTDRefund of the amount with interest along with other appropriate reliefsAUTHORITY16/08/2025
SABYASACHI DAS MAHAPATRA vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTD. & OTHERSThe complainant claims full refund of all payments made, along with interest, and litigation costs, and any other reliefs deemed appropriate.AUTHORITY16/08/2025
Karunanidhi Trichy vs OZONE URBANA INFRA DEVELOPERS PVT LTDRefund with interestAUTHORITY16/08/2025
Jose Thompson vs OZONE URBANA INFRARefund with interest and closure of loanAUTHORITY16/08/2025
TASNEEM EBRAHIM RASSIWALA vs M/S.OZONE URBANA AND OTHERSRefund of the amount with interest along with other appropriate reliefsAUTHORITY16/06/2026
Mohammed Asif Khan vs M/S.OZONE URBANARefund the Token Amount of Rs. 4,00,000/- and the Loan Amount Disbursed by HDFC Bank amounting to Rs. 62,00,000/- along with interest at 21% per annum from May 2023AUTHORITY16/06/2026
Jogi George vs OZONE URBANA INFRA DEVELOPERS AND 8 OTHERSrefund amount including pre-emi paid with interest as per section 19 of RERA ActAUTHORITY16/05/2025
NAVEEN RAJESHKUMAR vs M/S.OZONE URBANAInterest for delay in delivering the unitAUTHORITY16/03/2026
Dharmendrakumar Harihar Desai vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund with compensation and cancellation of loanAUTHORITY16/03/2023
Sundaram vs M/S.OZONE URBANA INFRA DEVELOPERSHDFC loan cancellation or transfer the loan to builder name, get my investment back, pre-emi's paid from my pocket along with interest and penaltyAUTHORITY16/02/2026
SHAFIULLA SAMEER KHAN vs M/S.OZONE URBANA AND OTHERSRefund and closure of loanAUTHORITY16/02/2026
Sadiq Suleman vs M/S.OZONE URBANA AND OTHERSRefund with interest and closure of loanAUTHORITY16/02/2026
Prakash Virkar vs M/S.OZONE URBANA INFRARefund of full amount paid in December 2018 with interestAUTHORITY16/02/2026
Samir Kumar vs M/S.OZONE URBANA INFRARefund with interest and closure of loanAUTHORITY16/02/2026
Sudha V Iyer vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDTo award Delay Compensation of Rs 30,00,000/- (Thirty Lakhs Only) for delay of 58 months in delivery of Possession over Ozone Urbana Pavillion Apartment K -303, a 3BHK Apartment having 1540 Square Ft.AUTHORITY16/02/2023
Veer raj naik vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDOccupancy certificates and Promised amenitiesAUTHORITY15/09/2022
Ganesha AG Batta vs M/S.OZONE URBANA AND OTHERSWherefore, the Applicant respectfully prays that this Hon’ble Authority may be pleased to allow the instant complaint and award: a.cancellation of the Agreement of Sale dated 19.08.2015; b.Refund ofAUTHORITY15/06/2026
Chakravarthi Mohan vs M/S.OZONE REALTORS PVT LTDDirect the Respondents to hand over Apartment ready to occupy, interest on delay period, cost of damages and litigation cost...AUTHORITY15/06/2026
Smt Anupama Mohan vs M/S.OZONE REALTORS PVT LTDDirect the Respondents to hand over Apartment ready to occupy, interest on delay period, cost of damages and litigation cost.AUTHORITY15/06/2026
Shaik Saleem Ahmed vs M/S.OZONE URBANA AND OTHERSRefund with interest and closure of bank loanAUTHORITY15/06/2026
Minal Vikram Rao vs M/S.OZONE URBANA AND OTHERSRefund with interest and buyback amount along with closure of loanAUTHORITY15/06/2026
JOGI GEORGE vs OZONE URBANA INFRA DEVELPERSrefund amount including pre-emi paid with interest as per section 19 of RERA ActAUTHORITY15/05/2025
Kali Venkata Kiran Kumar vs OZONE URBANARefund with interest of amount paid by meAUTHORITY15/05/2025
Mr Rohit Chauhan vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDReturn of amount for L 303 + interest + close HDFC Loan + compensation for delay till OC + return of booking amount for new 1 BHK + compensation under section 72AUTHORITY15/03/2023
Arindam Lahiri vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund of application money of Rs. 75,000 along with applicable interestAUTHORITY15/03/2023
Mohammed Nurain Megoon vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund of amounts paid by me with interest and compensationAUTHORITY15/03/2023
Manisha Gupta vs Ozone Urbana Infra Developers Pvt Ltdpenalty be imposed on the directors, managers and other officer of OzoneAUTHORITY15/02/2025
Jaywant Chandrashekar Prabhu vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDCancellation of loan and compensationAUTHORITY14/09/2023
Mini John vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund of amount with interest and payment of PEMI by the buildersAUTHORITY14/09/2023
Docca V Phanikumar vs Ozone Urbana Infra Developers Pvt LtdProtection of my rights and enforcing the recent SC ruling on the builder in compensating with interest such as maintenance, Pre-EMI, property tax and othersAUTHORITY14/07/2026
Rajeev Narayan vs Ozone Urbana Infra Developers Pvt Ltd1. Obtain OC, facilitate khata transfer and form Association 2. Deliver all three Club houses 3. Bring club house charges under Township CAM 4. Fix common area design and construction defectsAUTHORITY14/07/2026
Shaila Manohar vs Ozone Urbana Infra Developers Pvt LtdImmediate arrest of the Ozone group MD and Chairman, impose fine and penalty on daily basis, confiscate of licenceAUTHORITY14/07/2026
Anil Kumar Muthya vs Ozone Urbana Infra Developers Pvt LtdPossession of flat and interest on delay periodAUTHORITY14/07/2026
Urbana Aura Apartment Owners Association vs Ozone Urbana Infra Developers Pvt Ltd1. Handover the Corpus fund 2.Refund money collected towards maintenance (INR 50,91,201) 3.Reimburse expenditure by owners. 4. Commission facilities 5. Deliver club houses 6. Township Infra managementAUTHORITY14/07/2026
Milind Sabnis and Monica Chitnis vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund of the Amount and compensationAUTHORITY14/06/2023
Ramaswamy Srikanth vs OZONE URBANARefund of entire amount plus interestAUTHORITY14/05/2025
ERROL JOHN NORONHA vs OZONE URBANAREQUEST KARNATAKA RERA AUTHORITY TO IMPOSE Section 64 of the RERA ActAUTHORITY13/12/2023
ERROL JOHN NORONHA vs OZONE URBANAIMMIDIATE ARREST AND/OR CONFISCATION OF LICENSE AND IMPOSE FINE ON THE PROJECT EVERYDAY THERE IS A DELAY FOR NON-PAYMENTAUTHORITY13/12/2023
ANIRBAN DAS vs OZONE URBANA INFRA DEVELOOPERS PVT LTDI need my refund/compensation immediately to sustain further. Pls help me and my family. Need a good judgement from you. I have all faith on RERA admin. Regards. ANIRBAN DAS 9903023756, anirban.das07AUTHORITY13/10/2025
NIKUNJA KUMAR PARIDA vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDI want to exit from the project and builder should refund my money with compensation for delay @ 18% interest including all credit notes issued by the builder.AUTHORITY13/09/2023
Sunil Ravindran vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDBuilder has to hand over the flat and pay compensation towards the rent that we have been currently payingAUTHORITY13/09/2023
Amar Nath Banerjee vs OZONE URBANA INFRADirect the Respondents to refund all payments made by the Complainant, including EMIs, and repay the outstanding home loan associated with Account No.41062195729, obtaining an NOC from SBIAUTHORITY13/08/2025
Usha Vijaykumar vs ozone urbanarefund principle amount with interest as per section 19 of RERA Act along with amount paid for interiorsAUTHORITY13/08/2025
PARIXIT SHUKLA vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTD.Refund the amount paid to promoter and bank in the form of Pre-EMI along with interest as per section 19 of the RERA ActAUTHORITY13/05/2025
Vinod Jaiswal vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund of Rs. 77,511 deducted as TDS, Compensation, Damages, Costs of ProceedingsAUTHORITY13/05/2024
Reddipalli Anil Kumar vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund with interestAUTHORITY12/09/2023
SHIV SAGAR vs OZONE URBANA INFRA DEVELOPERS PVT LTD(1) Relief from PEMI , (2) Compensation and Interest from the promoter at the prescribed rate as per the RERA.AUTHORITY12/09/2022
Amit Kumar vs OZONE URBANA INFRA DEVELOPERS PVT LTD.Builder has promised flat possession by Dec 2020 but currently they are not sure when it will be finished. I want them to close my loan and relieve me from this Project.AUTHORITY12/09/2022
KANISHKA KUMAR vs OZONE URBANA INFRA DEVELOPERS PVT LTDRefund of the Money paid along with CompensationAUTHORITY12/07/2022
ERROL JOHN NORONHA vs ERROL JOHN NORONHA & DELFINA NORONHAPLEASE REFUND ALL THE MONIES PAID TILL DATE AND PAY THE INTEREST OF 18% FROM AMOUNT PAID DATEAUTHORITY12/07/2022
Sudhir R vs OZONE URBANA INFRA DEVELOPERS PVT LTDCompensation for delay and related losses sufferedAUTHORITY12/07/2022
DINESH SINGH RAJPUT vs Ozone Urbana Infra Developers Pvt Ltd1) Earliest handover/registration for A-604 preferably by May 2024 and refund of all excess payments. Or 2)Refund of all amount paid including interest and credit notes if no handover by May 2024AUTHORITY12/05/2025
P R Subramania Prabhu vs Ozone Urbana Infra Developers Pvt Ltdhandover the project/flatAUTHORITY12/05/2025
Ramesh Chittapragada & Nagasarada Rebbapragada vs Ozone Urbana Infra Developers Private LimitedBuyback amount + interest and closure of loanAUTHORITY12/03/2024
Sandeep Kumar Sharma vs OZONE URBANA INFRADirect the respondents to cancel the agreement of sale and to refund of amount with interest and to clear the home loan and to pay petition cost of Rs.1,00,000/-AUTHORITY12/01/2026
Pooja Sanjay vs OZONE URBANA INFRA DEVELOPERS PVT LTDTo pay compensation for delay of 5 years in handing over possession of the subject flat quantified at sum of Rs 30 lakhs.AUTHORITY11/10/2022
Sherry Joshua & Ann Joshua vs OZONE URBANA INFRA DEVELOPERS PVT LTDCompensation for delay and related losses suffered and full refundAUTHORITY11/10/2022
Abraham K Varughese vs OZONE URBANA INFRA DEVELOPERS PVT LTDCompensation for delay and relates losses sufferedAUTHORITY11/10/2022
Phalaksh Shrishail Walishetty vs OZONE URBANA INFRA DEVELOPERS PVT LTDFull refund of the booking amount with compensation and Interest and close the bank loan.AUTHORITY11/10/2022
Sonal Kuruwa vs OZONE URBANA INFRA DEVELOPERS PVT LTDRefund of entire amount of Rs.8,93,424 Paid with interest as per sec 18 of RERA Act, refund of PEMIs amounts paid, closure of loan, repay litigation fees incurred by the Complainants & other reliefs.AUTHORITY11/08/2025
RAJESHWARI ANANDA & ANANDA GUNDURAO vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITED & ANOTHERDelay Period Interest from BuilderAUTHORITY11/07/2024
Kanchan Lata Sharma & ABHISHEK SHARMA vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDDirect Respondent Developer to Refund the entire sale consideration with rera prescribed rate of interestAUTHORITY11/07/2024
Arup kumar Das vs OZONE URBANA INFRA DEVELOPERS PVT LTDRefund of the entire amount paid along with interestAUTHORITY11/07/2022
Jithu Varghese vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTDto get project handed over and refund excess money collected with interest.AUTHORITY10/12/2025
MR DEEPK LINGWAL vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTDBreach of Buyback Agreement hence seeking refund of Own Contribution, Buyback Amount, PEMI paid and LoanAUTHORITY10/12/2024
MR VAIBHV VINOD SOMAL vs M/S.OZONE URBANA INFRA DEVELOPERSPayment and Closure of loan and interestAUTHORITY10/12/2024
MR JOHN KUNCHANDY AND ANOTHER vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTDRefund with interest of own contribution and buyback amount along with closure of loanAUTHORITY10/12/2024
Deepa Ghanshyam Bhatia vs M/S.OZONE URBANA INFRA DEVELOPERS AND OTHERSRefund with interest and closure of loanAUTHORITY10/11/2025
Deepa Ghanshyam Bhatia vs M/S.OZONE URBANA INFRA DEVELOPERS AND OTHERSRefund with interest and closure of loanAUTHORITY10/11/2025
Deepa Ghanshyam Bhatia vs M/S.OZONE URBANA INFRA DEVELOPERS AND OTHERSRefund with interest and closure of loanAUTHORITY10/11/2025
Deepa Ghanshyam Bhatia vs M/S.OZONE URBANA INFRA DEVELOPERS AND OTHERSRefund with interest and closure of loanAUTHORITY10/11/2025
RUPESH KUMAR vs M/S.OZONE URBANA INFRA DEVELOPERS AND OTHERSClosure of loanAUTHORITY10/11/2025
DILIP CHANDRA vs OZONE URBANA INFRA DEVELOPERS PVT LTDDirecting to deliver the possession of the finished flat immediately and pay interest and damages on the delayed possession OR to repay Rs.7,26,92,629/- as compensaiton.AUTHORITY10/11/2022
Dr Asha Shankar Bhandary & H. SHANKARA BHANDARY vs OZONE URBANA INFRA DEVELOPERS PVT LTD AND 4 OTHERSProject completion + delay compensation + Compensation towards mental agony + Pay loss of rental income + Pay interest on Pre EMI in toto + Pay legal expenses as explained in detail in the complaintAUTHORITY10/10/2022
Punna kariadan Inder vs M/S.OZONE URBANADirect the respondents to cancel the agreement of sale and to refund of amount with interest and to clear the home loan and to pay petition cost of Rs.1,00,000/-AUTHORITY10/06/2026
Sabyasachi Das Mahapatra vs M/S.OZONE URANARequest RERA to approve my request to cancel the booking so that I can request for full refund from the developerAUTHORITY10/06/2026
Srinivasan Padmanabhan vs M/S.OZONE URBANA AND OTHERSrefund amount with interest as per section 19 of RERA ActAUTHORITY10/06/2026
Sanjay Ganpat Ingle vs M/S.OZONE URBANA AND OTHERSRefund with interest and closure of loanAUTHORITY10/06/2026
Deepthi Dinakar vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTD AND OTHERSa)Execution of cancellation of the Agreement of Sale dated 26.04.2016 and Construction Agreement dated 26.04.2016. b)Refund of Rs. Refund Rs 4,27,326/- (Rupees Four Lakhs Twenty Seven Thousand ThreeAUTHORITY10/06/2025
Anhul Chauhan vs OZONE URBANARefund with interest of buyback and PEMI amount and closure of loanAUTHORITY10/03/2025
Sangeeta Jaiswal vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDI want full refund of the amount paid with interest and closure of bank loan with no liability on me.AUTHORITY10/03/2023
S Parthasarathy vs OZONE URBANA INFRA DEVELOPERS PVT LTDRefund + Interest+ compensationAUTHORITY09/12/2023
DR RANJAN SARKAR vs OZONE URBANA INFRA DEVELOPERS PVT LTDCANCELLATION AND REFUND IN FULL WITH COMPENSATION AND INTERESTAUTHORITY09/09/2023
Shadagopan Eyunni vs OZONE URBANA INFRA DEVELOPERS PVT LTDCANCELLATION AND REFUND IN FULL WITH INTEREST AND PENALTYAUTHORITY09/09/2023
Vaibhav Shah, Rekha Kirit Shah and Kirit U Shah vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund and compensation.AUTHORITY09/09/2023
Vasant Shenoy vs Ozone Urbana Infra Developers Private Limiteda.Execution of cancellation of the Agreement of Sale dated 27.11.2017. b.Refund of the entire amount paid by the Complainant as annexed in Annexure C with 11% rate of interest from the due date tilAUTHORITY09/07/2024
Narendra Babu Rajagopal & Roopa Hanumantha Rao vs Ozone Urbana Infra Developers Private LimitedRefund with interest and closure of loan and any liability associated with itAUTHORITY09/07/2024
Bharatkumar Ravishankar Sharma & Sonali Sharma vs Ozone Urbana Infra Developers Private LimitedDirect Developer to Refund the entire sale consideration with rera prescribed rate of interestAUTHORITY09/07/2024
Abhilash Kumar V S vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTD & OTHERSRefund of all the amounts paid to the respondent along with compensation and interest.AUTHORITY09/04/2025
Paritala Sivaramakrishna vs M/S.OZONE URBANA INFRA DEVELOPERS AND OTHERSrefund amount including pre-emi paid with interest as per section 19 of RERA ActAUTHORITY09/04/2025
Mahesh Ram Joshi vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTDrefund amount including pre-emi paid with interest as per section 19 of RERA ActAUTHORITY09/04/2025
Bharat Kumar Sharma vs Ozone Urbana Infra Developers Pvt LtdInitiate penalty proceedings under Section63 of the RERA Act against the Respondent Company and its DirectorsAUTHORITY09/03/2026
Kanchan Lata Sharma vs Ozone Urbana Infra Developers Pvt LtdInitiate penalty proceedings under Section 63 of the RERA Act against the Respondent company and its directorsAUTHORITY09/03/2026
Vinod Kumar vs M/S.OZONE URBANARefund of the amount with interest along with other appropriate reliefsAUTHORITY09/03/2026
PAVAN KUMAR N vs M/S.OZONE URBANAinterest for delay in delivering the unitAUTHORITY09/03/2026
Malarmala Karunanithi vs M/S.OZONE URBANARefund of Rs.24,63,180, Interest at the rate of 18% and Compensation of Rs.10,00,000AUTHORITY09/03/2026
SHASHILATA VASANT SUVARNA vs M/S.OZONE URBANA AND OTHERSRefund with interest and closure of loanAUTHORITY09/03/2026
Shashikant Gupta vs OZONE URBANA AND OTHERSWherefore, the Applicant respectfully prays that this Hon’ble Authority may be pleased to allow the instant complaint and award: a.cancellation of the Agreement of Sale dated 24.01.2018; b.Refund ofAUTHORITY09/02/2026
Monarch Limaye vs M/SOZONE URBANAReturn of amount paid along with the interestAUTHORITY09/02/2026
Vivek Kumar Agrawal vs M/S.OZONE URBANA AND ANOTHERRefund of the sum of Rs. 24,17,549 to the Complainant with interest at 12%, to pay sum payable including the interest and penalty being the repayment of the balance loan to HDFC Ltd., damages & CostAUTHORITY09/02/2026
Pradeep Kumar Mishra vs M/S.OZONE URBANArefund amount including pre-emi paid and interest as per section 19of RERA ActAUTHORITY09/02/2026
Pradeep Kumar Mishra vs M/S.OZONE URBANArefund amount including pre-emi paid and interest as per section 19of RERA ActAUTHORITY09/02/2026
Venkata S Musti vs M/S.OZONE URBANA INFRA AND OTHERSRefund with interest and closure of loanAUTHORITY09/02/2026
Vishnu Kiran Chirala & Padmaja Easwarapragada vs M/s Ozone Urbana Infra Developers Private LimitedRefund with interest and closure of loanAUTHORITY09/02/2024
Vishnu Kiran Chirala & Padmaja Easwarapragada vs M/s Ozone Urbana Infra Developers Private LimitedRefund with interest, closure of loanAUTHORITY09/02/2024
Subhashree Saha vs ozone urbanaRefund of the amount with interest along with other appropriate reliefsAUTHORITY08/12/2025
RAJESHWARI SHEKARAYYA HASANABADIMATH vs M/S OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund with interest and compensationAUTHORITY08/11/2023
Mrunal Rangnath Vidhate vs OZONE URBANARefund of entire amount with interest & costs and other appropriate reliefsAUTHORITY08/10/2025
Lakshmanan Balakrishnan vs OZONE URBANA INFRA DEVELOPERS PVT LTDPlease issue order for them to refund my amount, Plus Impose damages on OZONE. They sold that unit which I cancelled, but they did not pay me. This is highly irregular, amounts to criminal chargesAUTHORITY08/07/2023
Jagadeesan P vs OZONE URBANA INFRA DEVELOPERS PVT LTDHumbly requesting the Hon'ble RERA to direct the Builder to pay the dues and continue reimbursing Pre EMIs till possession of apartmentAUTHORITY08/07/2023
Mohit Sharma & Akansha Sharma vs OZONE URBANA INFRA DEVELOPERS PVT LTDINR 1,85,61,699/- for refund and different compensationsAUTHORITY08/07/2023
P R Subramania Prabhu vs P R SUBRAMANIA PRABHU & K S REKHARs 5,00,000 (Rupees Five lakhs Only) as compensation for delayed handing over with interest till date of realization.AUTHORITY08/07/2022
RAVISHANKAR MALLIKARJUNAPPA GEER vs M/S.OZONE URBANA AND OTHERSRefund with interest with other appropriate reliefsAUTHORITY08/06/2026
PREM KALYAN vs M/S.OZONE REALTORSComplete refund with an interestAUTHORITY08/06/2026
Monika Jain vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund and CompensationAUTHORITY08/01/2024
H S GILL vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDComplete refund of the amount paid by us or on our behalf along with Pre-EMI with interest for the sameAUTHORITY07/09/2023
Sunny Shende vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund with interestAUTHORITY07/09/2023
Madhav Rangachari vs OZONE URBANA INFRA DEVELOPERS PVT LTDFull compensation with interest for delay, speedy completion of project and legal action against builders for false promises.AUTHORITY07/07/2022
Bhavna Raju sadhwani vs OZONE URBANA INFRA DEVELOPERS PVT LTDfull refund and balance compensation with damages for mental agonyAUTHORITY07/07/2022
BS Chauhan vs OZONE URBANA INFRA DEVELOPERS PVT LTDSir, please help us get back our money with interest from the builder.AUTHORITY07/07/2022
Anirudh Iyengar vs M/s Ozone Urbana Infra Developers Private LimitedFull refund with interestAUTHORITY07/02/2024
Jayatheertha Joshi & Madhura Jayatheertha Joshi vs M/s Ozone Urbana Infra Developers Private LimitedRefund of amount, with repayment of PEMI and closure of loanAUTHORITY07/02/2024
Jayatheertha Joshi & Madhura Jayatheertha Joshi vs M/s Ozone Urbana Infra Developers Private LimitedRefund of amount with interest , refund of Pemi paid and closure of loanAUTHORITY07/02/2024
Nagaraj Shashi Kiran vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund with interest and compensationAUTHORITY06/11/2023
Parijat Saurabh vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund with interestAUTHORITY06/11/2023
Pratishta Gupta vs M/s.Ozone Urbana Infra Developers Pvt Ltd and othersRefund with interest, Exit, breach of agreementAUTHORITY06/10/2025
Pavithra Raghunath vs M/s.Ozone Urbana Infra Developers Pvt Ltd and othersExecution of cancellation of Agreement for Sale, refund of amount paid, compensation, payment of all EMIs, closure of loan account, costs of proceedingsAUTHORITY06/10/2025
Karabi Bora vs M/s.Ozone Urbana Infra Developers Pvt Ltd and othersCancellation of Agreements, Exit from Project, Compensation, Payment of Pre-EMIs, Closure of loan account, Payment of Penalties imposed by M/s Indiabulls Housing Finance Limited, Costs of proceedingsAUTHORITY06/10/2025
KRISHNAN BHALAJI vs KRISHNAN BHALAJIRefund of all monies paid to PromoterAUTHORITY06/10/2025
SADANAND SHASTRI vs OZONE URBANA INFRA DEVELOPERS PVT LTDTo refund entire Agreement of Sale Amount including PEMI and damages along with interest for a period of 5 years i.e. Rs 1,40,00,000/- (Rupees One Crore Forty Lakhs Only) immediately to ComplainantsAUTHORITY06/10/2022
MANNUR GANDHI vs M/S.OZONE URBANA INFRA DEVELOPERS AND ANOTHERCompletion of project and handover of possession and interest on delay period.AUTHORITY06/08/2024
MR MANNUR GANDHI vs M/S.OZONE URBANA INFRA DEVELOPERS & ANOTHERCompletion of project and handover of possession and interest on delay period.AUTHORITY06/08/2024
MR MANNUR GANDHI vs M/S.OZONE URBANA INFRA DEVELOPERS & ANOTHERCompletion of project and handover of possession and interest on delay period.AUTHORITY06/08/2024
Vikram Jayaram Kadri vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDI am seeking full refund of all the PEMI’s paid by me and request RERA to provide a stay order so I can stop paying any further PEMI until occupancy.AUTHORITY06/06/2023
Balram Parath vs m/s.ozone urbana and othersRefund with interest and closure of loanAUTHORITY06/04/2026
Sivaraj Sivarama Krishnan vs M/S.OZONE URBANA AND OTHERSRefund with interestAUTHORITY06/04/2026
VISHAL VENU SOMAL vs M/S.OZONE URBANARefund and closure of loanAUTHORITY06/04/2026
Abdul Samad punekar vs M/S.OZONE URBANA AND OTHERSRefund and Closure of LoanAUTHORITY06/04/2026
KUNAL PATEL vs M/S.OZONE URBANA AND OTHERSRefund with interest and closure of loanAUTHORITY06/04/2026
Vikram Jayaram Kadri vs Ozone Urbana Infra Developers Private LimitedI am seeking full refund of all the money paid to promoter i.e. amount released by bank and PEMI’s paid by me to the bank.AUTHORITY06/02/2024
Malati Harish vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDre-payment of Loan and pay back PRE-EMI money paid with interest and compensationAUTHORITY06/02/2023
Monali Ramakant Gaikwad vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund of entire amount received by builder with interest as per RERA & clear bank loan amount taken in the name of complainantsAUTHORITY06/01/2023
TOVINAKERE DWARAKANATH VIVEK vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDI seek complete Refund of the amount paid along along with interesting closure of the loanAUTHORITY06/01/2023
Gourvendu Saxena vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund, compensation and exit from project.AUTHORITY05/09/2023
Gourvendu Saxena vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund along with compensation and exit from project with closure of loan account.AUTHORITY05/09/2023
Kamini vs Ozonerefund amount including pre-emi paid and interest as per section 19of RERA ActAUTHORITY05/08/2025
Prasanna S Shetty vs M/S.OZONE URBANA AND OTHERSCancellation of Agreements, Return of amount, exit from the project, Closure of Bank account, payment of outstanding dues and PEMIs to IHFLAUTHORITY05/06/2026
Mohamed Usman Parveez Yaseen vs M/s.Ozone Urbana Infra DevelopersRefund with interestAUTHORITY05/06/2026
Harshit Dwivedi vs M/S.OZONE URBANATo refund Rs Total advance amount of Rs 77,22,872/- and PEMI Rs 5,79,822 along with compensation and interestAUTHORITY05/02/2026
AMIT MISTRY vs M/S.OZONE URBANA AND OTHERSRefund of money paid with buyback amount and interest and closure of loanAUTHORITY05/02/2026
Deepthi Kurra vs M/S.OZONE URBANA AND OTHERSComplainant seeks full refund of all amounts paid along with interest.AUTHORITY05/02/2026
SITENDER KUMAR vs M/S.OZONE URBANA AND OTHERSRefund with interest and closure of loanAUTHORITY05/02/2026
Akshatha Mohan vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRepay the bank and Customer total money and Cancel the propertyAUTHORITY04/12/2023
Nithin Shet vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDCompensation for delay and relaed losses sufferedAUTHORITY04/11/2022
Saravanan Venkataraman vs OZONE URBANA INFRA DEVELOPERS PVT LTDDirecting the Respondent Builder to refund the sum of Rs. 60,60,214/- (Rupees Sixty Lakhs Sixty Thousand Two Hundred and Fourteen Only) along with other Monies paid by the Complainant.AUTHORITY04/11/2022
Ajith Murthy vs OZONE URBANA INFRA DEVELOPERS PVT LTDPayment of PRE-EMI dues & delay compensation, to the tune of Rs. 39,55,541/- along with direction for completion of the Apartment and hand over of the possessionAUTHORITY04/11/2022
Ajith Murthy vs OZONE URBANA INFRA DEVELOPERS PVT LTDPayment of PRE-EMI dues & delay compensation, to the tune of Rs. 39,55,541/- along with direction for completion of the Apartment and hand over of the possessionAUTHORITY04/11/2022
Venkat Rao Gopishetty vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDCancellation of Agreements and Refund of AmountAUTHORITY04/09/2023
Mallikarjuna Reddy G R vs OZONE URBANA INFRA DEVELOPERS PVT LTDThe Complainant prays that the Hon'ble Tribunal be pleased to fully refund an amount of Rs 1,20,00,000/- (One Crore Twenty Lakhs Only) from the Respondent for breach of Agreement of Sale 05-08-2014AUTHORITY04/09/2023
Kamini vs ozone urbanarefund amount including pre-emi paid and interest as per section 19of RERA ActAUTHORITY04/08/2025
Shahul Hameed Dasthagir vs Ozone Urbana Infra Developers Private LimitedRefund and Compensation of the loss incurred (approx 20 Lakh Paid as Interest to the Financier for this unit)AUTHORITY04/06/2024
Dharmendran Palani Swamy & Nagratna Dharmendran vs Ozone Urbana Infra Developers Private Limited & anothercomplete refund of the amount paid along with Pre_EMI I Have paid along with interest for the same.AUTHORITY04/06/2024
Pawan Jaiswal & Vidhi Jaiswal vs Ozone Urbana Infra Developers Private LimitedBuilder must pay the PEMI to bank till the flat Handover/Possession and pay us the interest and amount which I paid as part of PEMI to bank till now along with compensation for delay penalties.AUTHORITY04/06/2024
Rajesh Rao C V vs OZONE URBANArefund amount with interest as per section 19of RERA ActAUTHORITY04/03/2026
Vijay Kumar M V vs OZONE URBANA INFRA DEVELOPERS PVT LTDRefund with interestAUTHORITY04/03/2025
Anhul Chauhan vs OZONE URBANA INFRA DEVELOPERSRefund with interest of buyback amount, PEMI and closure of loanAUTHORITY04/03/2025
Sreejith Kandoth Nallakandy vs OZONE URBANA INFRA DEVELPERS PVT LTDRefund with interestAUTHORITY04/03/2025
Puravoor Sanjeev Unnikrishna Panicker vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund of invested amount with promised return and interest and closure of loan in my nameAUTHORITY04/03/2024
ABHISEK SEN GUPTA vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITEDRefund of initial deposit + Guaranteed profit and closure of loanAUTHORITY03/12/2024
Bhavna Gupta vs OZONE URBANA INFRA DEVELOPERS PVT LTDCompensation and refund of invested money with interestAUTHORITY03/11/2022
Putrevu Subramanyam vs OZONE URBANA INFRA DEVELOPERS PVT LTDCompensation for delay and related losses sufferedAUTHORITY03/11/2022
Rajesh Verma vs OZONE URBANA INFRA DEVELOPERS PVT LTDTo pay compensation for delay to the tune of Rs 25,00,000/- (Twenty Five Lakhs Only) along with interest and damages as quantified at the disposal of this complaint by this authority.AUTHORITY03/10/2022
RAM BABU SINGH vs OZONE URBANA INFRA DEVELOPERS PVT LTDCompensation required from 6th December 2019 onwards till dateAUTHORITY03/10/2022
NRA Prasad vs OZONE URBANA INFRA DEVELOPERS PRIVATE LIMITED & SIX OTHERSExit along with refundAUTHORITY03/08/2023
MAHESH RAM JOSHI vs OZONE URBANACancellation of unit and Refund of amount + PEMI paid on behalf of the builder with interest andAUTHORITY03/05/2025
Pawan Kumar vs M/S.OZONE URBANA AND OTHERSRefund with interest with other appropriate reliefsAUTHORITY03/03/2026
ASHOK KALYAN TAVVA vs M/S.OZONE URBANARefund Rs. 9,51,337/- along with interest amounting to Rs. 16,64,840/- ii) refund of the PEMIs paid by the Complainant i.e., Rs. 26,55,046/- iii) to pay a compensation of Rs. 10,00,000/-AUTHORITY03/03/2026
KUNAL V BESWAL vs OZONE URBANA INFRA DEVELOPERS PVT LTD & ANOTHERRefund of entire amount of Rs.11,02,585 with interest as per sec 18 of RERA Act, refund of PRE-EMI amounts paid, closure of loan, repay litigation fees incurred by the complainant & other reliefsAUTHORITY02/12/2024
Vijaya Kumar Kidambi vs OZONE URBANA INFRA DEVELOPERS PVT LTDCompensation for delay and related losses suffered including Interest , Penalties , Rental loss , Mental AgonyAUTHORITY02/11/2022
Mr Syed Ajmal Ahmed vs OZONE URBANA INFRA DEVELOPERS PVT LTDCANCELLATION AND FULL REFUND WITH INTEREST AND PENALTIESAUTHORITY02/11/2022
MR T C GEORGE vs OZONE URBANA INFRA DEVELOPERS PVT LTDFULL CANCELLATION AND FULL REFUND WITH INTEREST AND PENALTYAUTHORITY02/11/2022
BR Vasuki vs OZONE URBANA INFRA DEVELOPERS PVT LTDPayment of PRE-EMI dues & delay compensation, to the tune of Rs. 41,97,071/- along with direction for completion of the Apartment and hand over of the possessionAUTHORITY02/11/2022
BR Vasuki vs OZONE URBANA INFRA DEVELOPERS PVT LTDPayment of PRE-EMI dues & delay compensation, to the tune of Rs. 46,31,222/- along with direction for completion of the Apartment and hand over of the possessionAUTHORITY02/11/2022
BR Vasuki vs OZONE URBANA INFRA DEVELOPERS PVT LTDPayment of PRE-EMI dues & delay compensation, to the tune of Rs. 42,58,697/- along with direction for completion of the Apartment and hand over of the possessionAUTHORITY02/11/2022
JAGADISH NAYAK vs OZONE URBANAClosure of Loan in accordance with the buyback agreementAUTHORITY02/09/2025
Sushanth Monteiro vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTDrefund of all the amount paid to the respondent and the amount paid Monthly to the loan account along with compensation and interestAUTHORITY02/06/2025
Divya G Prasad vs M/S.OZONE URBANA INFRA DEVELOPERS PVT LTD AND OTHERSrefund and execution of cancellation of sale agreementAUTHORITY02/06/2025
Atul Agarwal vs OZONE URBANACANCEL SALE AGREEMENT AND REFUNDAUTHORITY02/06/2025
Vishwanath Mayya KC vs M/S.OZONE URBANA INFRA AND OTHERSWherefore, the Applicant respectfully prays that this Hon’ble Authority may be pleased to allow the instant complaint and award: a.Execution of cancellation of the Agreement of Sale dated 29.03.2021.AUTHORITY02/02/2026
PRATITI DE vs M/S.OZONE URBANA INFRAIt is, therefore, in view of the facts narrated hereinabove, Complainants prays for the refund an amount of Rs.68,49,508/- (Sixty-Eight Lakh Forty-Nine Thousand Five Hundred Eight only) along with simAUTHORITY02/02/2026
Srinivas Satya Ramayanam vs M/S.OZONE URBANA INFRA DEVELOPERS & THERSThe complainant seeks full refund with interest, costs, and any other reliefs deemed appropriate.AUTHORITY01/12/2025
Chethan S vs M/S.OZONE URBANA INFRA DEVELOPERSRefund of Booking amount with Interest and damages amount and also closure of loan.AUTHORITY01/12/2025
Rahul Kumar vs OZONE URBANAPOSSESSION WITH DELAY PERIOD INTERESTAUTHORITY01/12/2025
Prashanth Panduranga vs OZONE URBANA INFRA DEVELOPERS PVT LTDRefund from the promoter with interestAUTHORITY01/09/2022
Vijayanand Paulraj vs Ozone Urbana Infra Developers Private LimitedRefund with interest + Closure of bank loanAUTHORITY01/07/2024
Abhilash Gautam vs OZONE URBANARefund the amount, close the loan and pay penalty and interest for severely delayed settlement.AUTHORITY01/01/2026

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (160 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190615/0002909
15-06-2019
Expecting RERA compliant fair compensation and justification for the delay of apartment handover and cheating on car parkingOzone UrbanaDISPOSED AO
CMP/190614/0003280
14-06-2019
Builder not closing the loan taken for the propertyOzone UrbanaDISPOSED AO
CMP/190714/0003496
14-07-2019
Withdrawal from project/ contract and full refund with interestOzone UrbanaDISPOSED AO
CMP/190708/0003516
08-07-2019
Breach of subvention terms as laid out in agreement- Burden of Pre-EMI transferred to Customer without property handoverOzone UrbanaDISPOSED AO
CMP/190730/0003755
30-07-2019
Builder abruptly stopped paying Pre-EMI to Bank, under 'subvention scheme'Ozone UrbanaDISPOSED AO
CMP/190815/0003911
15-08-2019
False Advertising - Open Parking allotted instead of advertised Closed parkingOzone UrbanaDISPOSED AO
CMP/190906/0004125
06-09-2019
Subvention Terms broken by the BuilderOzone UrbanaDISPOSED AO
CMP/191123/0004700
23-11-2019
Complaint Seeking cancellation of the Flat and refund of the entire money paid till date along with the pre-emi paid and compensationOzone UrbanaDISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectRSP DESIGN CONSULTANTS-1997Bengaluru, Karnataka 560001
ContractorJMC Projects (India) Ltd-1982Bengaluru 560025, Karnataka
Structural engineerNADIG CONSULTANT---

Builder track record

RERA filing

Ozone Urbana has 3 other K-RERA-registered projects in our records. 2 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹57.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Kasturba Road (IFSC HDFC0000009, a/c …8460). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kempegowda Int'l Airport5 km
Outer Ring Road / Manyata19 km
MG Road / city centre27 km
Whitefield IT hub29 km
Bellandur–Marathahalli belt31 km
Electronic City41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Ozone Urbana.
Ozone Urbana has 4 projects registered in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Devanahalli

Under The Sun – Luxury Villa Lifestyle By Fortius
Construction Of 423 Houses In Vijayappura & Devan

Major developers building in Devanahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.