Pune/Project record

MahaRERA · the public record

AMBER

Pune · YASHSAMRUDDHI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100009253

Delivery and registration

When is the project declared for completion?

AMBER is registered with MahaRERA as P52100009253 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100009253
Registered on22 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AMBER record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AMBER in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
AMBER1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2018Plans are submitted for revision of proposed extended floor. Plans are not approved from Pune Municipal Corporation (PMC) due to the issue of F.S.I potential given to the property

Location, Land & Connectivity

Located at Haveli, Pune, 411045. Per the filed land record, the plot is bounded to the north by 10, to the south by 10, to the east by 15 and to the west by 10. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Baner–Balewadi belt2 km
Hinjewadi Rajiv Gandhi IT Park7 km
Pune Junction / city centre9 km
Pune Int'l Airport (Lohegaon)14 km
Magarpatta / Hadapsar IT15 km
Kharadi / EON IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Baner

1 NEW Castle
possession by Sep 2026 · Chavda Realty LLP
17 East
possession by Sep 2026 · Platinum Properties
Downtown
possession by Sep 2026 · Samarttha Buildcon
Grace Avenue
possession by Sep 2026 · Trimurthy Narayan
Kavish Residency
possession by Sep 2026 · Damle Gandhe LLP
Rahul Altimus
possession by Oct 2026 · Rahul Construction Company

Major developers building in Baner

Other RERA-registered projects in Pune

Amber Wing C
possession by Mar 2029 · Saffron Developers
Amberwood Phase 1
possession by Dec 2028 · SMP Namrata Associates
Ambiience Vivanta
possession by Dec 2029 · Ambiience Developers
Ambition Pride
declared completion Apr 2024 · Ambtion Pride
Ambrosia Alley
possession by Jun 2027 · Ambrosia Landmark Private Limited
Ambrosia Galaxy
declared completion Nov 2025 · Divyasparsh Infra LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026