Pune/Project record

MahaRERA · the public record

CRYSTAL HEIGHTS

Pune · SATISH BORA AND ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2017declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2017

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100005326

Delivery and registration

When is the project declared for completion?

CRYSTAL HEIGHTS is registered with MahaRERA as P52100005326 and the promoter has declared completion for 31 Dec 2017.

31 Dec 2017

declared completion

105months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100005326
Registered on11 Aug 2017
Promoter-declared completion31 Dec 2017
Current statusCertificate Signed
Against todayabout 105 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CRYSTAL HEIGHTS record 2 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 2 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Satish Bora is the promoter of record on 88 projects registered with MahaRERA, 16 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

88projects

registered with MahaRERA

16flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CRYSTAL HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
G WING1G+831 Dec 2017

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Pune City, Pune, 411057. Per the filed land record, the plot is bounded to the north by S NO 176, to the south by S NO 175, to the east by S NO 177 and to the west by S NO 127. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park3 km
Baner–Balewadi belt5 km
Pune Junction / city centre15 km
Pune Int'l Airport (Lohegaon)17 km
Kharadi / EON IT Park20 km
Magarpatta / Hadapsar IT20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Satish Bora AND Associates is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Satish Bora AND Associates

Satish Bora AND Associates
Not filing quarterly progress reportsPune

Other RERA-registered projects in Wakad

ANP Memento
possession by Sep 2026 · Five Star Construction Company
Manor Crystal
possession by Sep 2026 · Oxford Infra Group
Park59
possession by Sep 2026 · Shiv Developers
Sensorium, Phase VI
possession by Sep 2026 · Joyville Shapoorji Housing Private Limit
Sonchandr Residency
possession by Sep 2026 · Chandan Ramdas Kate
Spring Residency
possession by Sep 2026 · Pritam Ashok Kachi

Major developers building in Wakad

Other RERA-registered projects in Pune

Crystal Hills
declared completion Mar 2025 · Anand Developers
Crystal Homes Phase - I
possession by Dec 2026 · Crystal Creations
Crystal Plaza
declared completion Jan 2023 · Shree Developers
Crystal Space
possession by Mar 2027 · SAI Samarth Developers
Crystal Spring
possession by Dec 2029 · Kishankumar Jugalkishor Kedia
Crystal Tower
possession by Dec 2026 · Jadhav Civil Project

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.