MahaRERA · the public record
Gravity
Pune · BHUJBAL BROTHERS CONSTRUCTION COMPANY
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2018
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52100013278
Delivery and registration
When is the project declared for completion?
Gravity is registered with MahaRERA as P52100013278 and the promoter has declared completion for 31 Dec 2018.
31 Dec 2018
declared completion
93months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100013278 |
| Registered on | 21 Sep 2017 |
| Promoter-declared completion | 31 Dec 2018 |
| Current status | Certificate Signed |
| Against today | about 93 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Gravity record 6 quarterly progress reports since registration.
6quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Completion date lapsed — the registered completion date has lapsed without a recorded finish.
- Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Bhujbal Brothers Construction is the promoter of record on 49 projects registered with MahaRERA, 8 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
49projects
registered with MahaRERA
8flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for Gravity in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| GRAVITY | 1 | G+4 | - |
Legal and disputes
What disputes are disclosed?
24 complaints are on the MahaRERA record for Gravity, with orders passed in 24 of them.
24complaints
24with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC005000000064496 | 14/08/2020 | ANAND PANDURANG BENDRE vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY A PARTNERSHIP FIRM THOUGH ITS PARTNERS | order passed |
| CC005000000064498 | 14/08/2020 | MR. ANAND PANDURANG BENDRE vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A PARTNERSHIP FIRM, THUGH ITS PARTNERS | order passed |
| CC005000000064500 | 14/08/2020 | MRS MEENU KISHORE BENDRE vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064521 | 18/08/2020 | MRS SUJATA SAKET THAKOOR vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064522 | 18/08/2020 | MRS SUJATA SAKET THAKOOR vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064502 | 15/08/2020 | MRS PRACHI AMOL PARGAONKAR vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064504 | 15/08/2020 | MAHESH KANTILAL BHAYANI vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY | order passed |
| CC005000000064505 | 15/08/2020 | MRS SONALI SANTOSH JADHAV vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064511 | 16/08/2020 | MR DEEPAK BHARAT CHAWARE vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064512 | 16/08/2020 | MR SANTOSHKUMAR V. PALAYIL vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIPFIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064513 | 16/08/2020 | MR SANTOSHKUMAR V.PALAYIL vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGISTERED PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064514 | 16/08/2020 | MR SANTOSHKUMAR V.PALAYIL vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064515 | 16/08/2020 | MR SANTOSHKUMAR V. PALAYIL vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064524 | 18/08/2020 | MR RAHUL VIKRAM RANADE vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064525 | 18/08/2020 | MRS PRACHI RAHUL RANADE vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064527 | 19/08/2020 | MRS SEEMA JEEVAN MORE vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064528 | 19/08/2020 | MR. AMOL SUDHAKAR LAHANE vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064530 | 19/08/2020 | MR MANOJ NARAYAN SHINDE vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064529 | 19/08/2020 | MR AMOL ASHOK DHONDSE vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064535 | 19/08/2020 | MR ANAND DURGADAS PIKLE vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064537 | 20/08/2020 | MR RAJESH PUKHRAJ RAKA vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064538 | 20/08/2020 | MR RAJESH PUKHRAJ RAKA vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064539 | 20/08/2020 | MR RAJESH PUKHRAJ RAKA vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
| CC005000000064565 | 29/08/2020 | Mrs Swati Abhijit Patani vs M/S BHUJBAL BROTHERS CONSTRUCTION COMPANY, A REGI PARTNERSHIP FIRM, THROUGH ITS PARTNERS | order passed |
Location, Land & Connectivity
Located at Haveli, Pune, 411045. Per the filed land record, the plot is bounded to the north by 18MT WIDE DP ROAD, to the south by H NO 6 PART, to the east by 12MTR 205 ROAD and to the west by SR NO 28. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Baner–Balewadi belt | 1 km |
| Hinjewadi Rajiv Gandhi IT Park | 6 km |
| Pune Junction / city centre | 10 km |
| Pune Int'l Airport (Lohegaon) | 14 km |
| Magarpatta / Hadapsar IT | 15 km |
| Kharadi / EON IT Park | 16 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.