MahaRERA Property Intelligence · Pune

KIRAN SUFAL

P52100027275 · WAKAD · promoter Kiran Creators Developers

Certificate SignedDue 29 Dec 2024

Delivery & Registration

MahaRERA registrationP52100027275
Registered on01 Dec 2020
Promoter-declared completion29 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Kiran Creators Developers is the promoter of record on 115 projects, of which 24 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
KIRAN SUFAL1G+13-
-1--

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202329 Dec 2024Construction work is not completed because of delayed in revised sanction.

Location, Land & Connectivity

Located at WAKAD, -, Haveli, Pune, 411057. Per the filed land record, the plot is bounded to the north by BY REMAINING PART OF SURVEY NO 110-1-1 AND 110-2, to the south by BY 18 MTR WIDE ROAD, to the east by BY REMAINING PART OF SURVEY NO 110-2 and to the west by BY PROPERTY OF KRIPLANI BUILDERS. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

M/S Kiran Creators & Developers Through Proprietor MR. Kashinath Ganesh Nehete is the promoter on 11 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every M/S Kiran Creators & Developers Through P project & its RERA track record →

Other flagged projects by M/S Kiran Creators & Developers Through P

M/S Kiran Creators & Developers Through Proprietor MR. Kashinath Ganesh Nehete
FlaggedPune
M/S Kiran Creators & Developers Through Proprietor MR. Kashinath Ganesh Nehete
Past its declared completion datePune
M/S Kiran Creators & Developers Through Proprietor MR. Kashinath Ganesh Nehete
FlaggedPune
M/S Kiran Creators & Developers Through Proprietor MR. Kashinath Ganesh Nehete
FlaggedPune
M/S Kiran Creators & Developers Through Proprietor MR. Kashinath Ganesh Nehete
FlaggedPune
M/S Kiran Creators & Developers Through Proprietor MR. Kashinath Ganesh Nehete
FlaggedPune

Other RERA-registered projects in Wakad

Fusion Towers Phase III
possession by Jul 2026 · Rama Synergy Spaces
ANP Bizsquare
possession by Jul 2026 · Five Star Vighnesh Associates
Olive Orchard
possession by Jul 2026 · Anandtara Properties
Fairmont
possession by Aug 2026 · Krishna Icon Skyscraper LLP
Varad Residency
possession by Sep 2026 · Vilas Bhagaji Arekar
ANP Memento
possession by Sep 2026 · Five Star Construction Company

Major developers building in Wakad

Other RERA-registered projects in Pune

Kiran Sufal Phase II
declared completion Jun 2024 · Landowner MR Santosh Appa Kalate AND Oth
Kiran Suyog
declared completion Dec 2018 · M/S Kiran Creators & Developers Thro
Kiran Swastik Building A
declared completion Jun 2026 · Kiran Creators AND Developers Private Li
Kiran Swastik Building B
possession by Oct 2028 · Kiran Creators AND Developers Private Li
Kirik Oriole Phase 1A
declared completion Sep 2020 · Kirik Enterprises
Kirik Oriole Phase 1B
declared completion Mar 2022 · Kirik Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026