MahaRERA Property Intelligence · Pune

MARVEL ZEPHYR BUILDING U

P52100010976 · promoter Marvel Landmarks Pvt

Certificate SignedDue 31 Jul 2018

Delivery & Registration

MahaRERA registrationP52100010976
Registered on31 Aug 2017
Promoter-declared completion31 Jul 2018
Current statusCertificate Signed
Against todayabout 96 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
U1G+13-

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000001041915/10/2017Rhythm Hemade vs Vishwajeet Jhavarorder passed
CC1260284014/05/2026Dr Dilip Vitthal Salunke vs MARVEL LANDMARKS PVT LTDpending / no order on file

Location, Land & Connectivity

Located at Pune City, Pune, 411014. Per the filed land record, the plot is bounded to the north by ZEPHYR BLDG T, to the south by PLOT BOUNDARY, to the east by PLOT BOUNDARY and to the west by PLOT BOUNDARY. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Kharadi / EON IT Park2 km
Pune Int'l Airport (Lohegaon)5 km
Magarpatta / Hadapsar IT5 km
Pune Junction / city centre9 km
Baner–Balewadi belt19 km
Hinjewadi Rajiv Gandhi IT Park24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Marvel Landmarks PVT LTD is the promoter on 7 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Marvel Landmarks PVT LTD

Marvel Landmarks PVT LTD
Past its declared completion datePune
Marvel Landmarks PVT LTD
FlaggedPune
Marvel Landmarks PVT LTD
FlaggedPune
Marvel Landmarks PVT LTD
FlaggedPune
Marvel Landmarks PVT LTD
FlaggedPune
Marvel Landmarks PVT LTD
FlaggedPune

Other RERA-registered projects in Kharadi

Satyam Shivam Phase 2
Not filing quarterly progress reports · possession by Sep 2026 · Vijayalaxmi Associates
The Collection - W2 And W7
possession by Sep 2026 · Bramhacorp Limited
Unique Youtopia Phase III
possession by Sep 2026 · Unique Associates
Spandan
possession by Oct 2026 · Evolve Infra
Ganga Platinum A
possession by Oct 2026 · Shree Balaji Associates Pune LLP
Percept Bounty 3
possession by Dec 2026 · Prime Estate

Major developers building in Kharadi

Other RERA-registered projects in Pune

Marvella
declared completion Aug 2023 · Arush Associates
Marvella
declared completion Dec 2025 · NEW Front EPS Ventures
Marwa
declared completion Dec 2025 · Northern Gates Realty Private Limited
Marwa Apartments
possession by Dec 2028 · Archway Properties
Mata Ramai Magaswargiya Sah Ggraharachana Sanstha Maryadit
declared completion Aug 2022 · Mata Ramai Magaswargiya Sah Graharachana
Mathura Heights
declared completion Mar 2026 · Rajmata Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.