Pune/Project record

MahaRERA · the public record

QBIX

Baner Taluka Haweli · Topline Buildtech

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

19units filed as unsoldInventory · 12 September 2026
31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100033154

Delivery and registration

When is the project declared for completion?

QBIX is registered with MahaRERA as P52100033154 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100033154
Registered on09 Feb 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for QBIX record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for QBIX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 September 2026

What the filings record, home by home

Read from MahaRERA on 12 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 1 homes carry one, and 19 of the 20 are recorded unsold.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
QBIX1G+1131 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Baner Taluka Haweli, Baner, Haveli, Pune, 411045. Per the filed land record, the plot is bounded to the north by 18M DP Road, to the south by Park Marina Society, to the east by Property of Pandurang Kalamkar and to the west by 18m DP Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Baner–Balewadi belt2 km
Hinjewadi Rajiv Gandhi IT Park7 km
Pune Junction / city centre9 km
Pune Int'l Airport (Lohegaon)14 km
Magarpatta / Hadapsar IT15 km
Kharadi / EON IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Baner

1 NEW Castle
possession by Sep 2026 · Chavda Realty LLP
17 East
possession by Sep 2026 · Platinum Properties
Downtown
possession by Sep 2026 · Samarttha Buildcon
Grace Avenue
possession by Sep 2026 · Trimurthy Narayan
Kavish Residency
possession by Sep 2026 · Damle Gandhe LLP
Rahul Altimus
possession by Oct 2026 · Rahul Construction Company

Major developers building in Baner

Other RERA-registered projects in Pune

Quality Royal Park
possession by Mar 2027 · Quality Construction
Qualityconstruction
declared completion Dec 2021 · Qualityconstruction
Quba Residency
possession by Dec 2028 · Quba Group
QUE 154 A AND B Wing
possession by Sep 2029 · UC Punawale Skyscrapers LLP
QUE 154 G Wing
possession by Sep 2029 · UC Punawale Skyscrapers LLP
QUE 914 Phase I
possession by Dec 2026 · Unique Choice Associates LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026