MahaRERA Property Intelligence · Pune

SHANKARVINAYAK APARTMENT

P52100016973 · BALEWADI · promoter And Construction

Certificate SignedDue 28 Dec 2022

Delivery & Registration

MahaRERA registrationP52100016973
Registered on26 Jun 2018
Promoter-declared completion28 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
SHANKARVINAYAK APARTMENT1G+615 Jun 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
28 Dec 202231 Jul 2021THERE WERE CHANGES IN PNE MUNICIPAL CORPORATION NORMS AND WE HAD PRIVILEGE OF TDR FROM CORPORATION
28 Dec 202228 Dec 2022We have applied for extension of the said project on 05/08/2021 having application no. EXT52100010678. As per order No. 24/2021 our project is under lapse category and we want to a

Location, Land & Connectivity

Located at BALEWADI, BALEWADI ROAD, Pune City, Pune, 411045. Per the filed land record, the plot is bounded to the north by FAVOLOSA, to the south by INTERNAL ROAD, to the east by ROAD and to the west by MR SUDARSHAN BANSAL PROPERTY. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Baner–Balewadi belt2 km
Hinjewadi Rajiv Gandhi IT Park3 km
Pune Junction / city centre13 km
Pune Int'l Airport (Lohegaon)16 km
Magarpatta / Hadapsar IT18 km
Kharadi / EON IT Park19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

A AND D Construction is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by A AND D Construction

Other RERA-registered projects in Baner

7 Business BAY
possession by Jul 2026 · Saaj Buildcon Private Limited
Maitreya
Not filing quarterly progress reports · possession by Jul 2026 · Vaibhav Shamrao Taro
Mercury
possession by Aug 2026 · SB Real Estate Private Limited
Aarambh
possession by Aug 2026 · ADI Realtors
Nancy Hillview A-1
possession by Aug 2026 · M/S Sarsan Aawishkar Properties
Truspace Platina
possession by Aug 2026 · Atharva Developments

Major developers building in Baner

Other RERA-registered projects in Pune

Shankeshawar Gold Palace
possession by Apr 2030 · BPO Uprise Lifestyle
Shankeshwar Business HUB Phase 1
possession by Dec 2027 · Arunita Developers
Shankeshwar Business HUB Phase II
possession by Dec 2027 · Arunita Landmarks
Shankeshwar Capital
possession by Dec 2027 · Nitin Chhaganlal Jain
Shankeshwar Crimson
declared completion Dec 2019 · Nitin Chhaganlal Jain
Shankeshwar Crystal
declared completion Dec 2025 · Shree Shankeshwar Highrisers PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026