MahaRERA Property Intelligence · Pune

SIDDHANT HEIGHTS

P52100034923 · NEAR SAI CANARY · promoter Siddhant Infrastructure Private

Certificate SignedDue 18 Feb 2025

Delivery & Registration

MahaRERA registrationP52100034923
Registered on28 Apr 2022
Promoter-declared completion18 Feb 2025
Current statusCertificate Signed
Against todayabout 17 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Siddhant Infrastructure Private is the promoter of record on 18 projects, of which 9 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
A WING1G+1918 Feb 2025
B WING1G+1918 Feb 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Senior Division Pune8632021Ext Five

Location, Land & Connectivity

Located at NEAR SAI CANARY , HIGH STREET TO BANGLORE HIGHWAY, Haveli, Pune, 411045. Per the filed land record, the plot is bounded to the north by REIDENTIAL PROJECT SAI CANARY, to the south by RESIDENTIAL PROJECT AMIT ASTIONIA, to the east by 12 METER INTERNAL ROAD AND PMC AMENITY SPACE and to the west by BALANCE PROPERTY OF SURVEY NO 42. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Baner–Balewadi belt2 km
Hinjewadi Rajiv Gandhi IT Park4 km
Pune Junction / city centre12 km
Pune Int'l Airport (Lohegaon)16 km
Magarpatta / Hadapsar IT18 km
Kharadi / EON IT Park18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Baner

7 Business BAY
possession by Jul 2026 · Saaj Buildcon Private Limited
Maitreya
Not filing quarterly progress reports · possession by Jul 2026 · Vaibhav Shamrao Taro
Mercury
possession by Aug 2026 · SB Real Estate Private Limited
Aarambh
possession by Aug 2026 · ADI Realtors
Nancy Hillview A-1
possession by Aug 2026 · M/S Sarsan Aawishkar Properties
Truspace Platina
possession by Aug 2026 · Atharva Developments

Major developers building in Baner

Other RERA-registered projects in Pune

Siddhant Ruturang
declared completion Jun 2022 · Chaitanya Buildcon
Siddharth
declared completion Dec 2024 · Kunal Developers
Siddharth
possession by Jan 2027 · Gangotree Homes
Siddharth Heights
declared completion Dec 2024 · Vardan Developers
Siddhesh Shreeram
declared completion Aug 2025 · Siddhesh Developers
Siddhesh - Yashoda
possession by Oct 2027 · Siddhesh Developers Unit - 1

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026