Pune/Project record

MahaRERA · the public record

The Balmoral Towers - Tower C, Phase II

Balewadi · Kasturi Spaces Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100047008

Delivery and registration

When is the project declared for completion?

The Balmoral Towers - Tower C, Phase II is registered with MahaRERA as P52100047008 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100047008
Registered on26 Sep 2022
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for The Balmoral Towers - Tower C, Phase II record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Kasturi Spaces is the promoter of record on 18 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

18projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for The Balmoral Towers - Tower C, Phase II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+38.

BuildingWingsFloorsDeclared completion
Tower C The Balmoral Towers Balewadi1G+3831 Dec 2028

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for The Balmoral Towers - Tower C, Phase II, with orders passed in 1 of them.

2complaints

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000025894401/06/2023Suryakanth Dhanawade vs Nahar Brothers Private Limitedorder passed
CC1260173826/03/2026Kasturi Spaces Private Limited vs Pravir Kumarpending / no order on file

Location, Land & Connectivity

Located at Balewadi, Balewadi, Haveli, Pune, 411045. Per the filed land record, the plot is bounded to the north by Tower B of the layout, to the south by Tower D of the layout, to the east by Adjacent S No 45 and to the west by Adjacent S No 45. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Baner–Balewadi belt2 km
Hinjewadi Rajiv Gandhi IT Park4 km
Pune Junction / city centre12 km
Pune Int'l Airport (Lohegaon)16 km
Magarpatta / Hadapsar IT18 km
Kharadi / EON IT Park18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Kasturi Spaces Private Limited is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Kasturi Spaces Private Limited

Kasturi Spaces Private Limited
FlaggedPune
Kasturi Spaces Private Limited
FlaggedPune

Other RERA-registered projects in Baner

1 NEW Castle
possession by Sep 2026 · Chavda Realty LLP
17 East
possession by Sep 2026 · Platinum Properties
Downtown
possession by Sep 2026 · Samarttha Buildcon
Grace Avenue
possession by Sep 2026 · Trimurthy Narayan
Kavish Residency
possession by Sep 2026 · Damle Gandhe LLP
Rahul Altimus
possession by Oct 2026 · Rahul Construction Company

Major developers building in Baner

Other RERA-registered projects in Pune

THE Benchmark
possession by Nov 2026 · Shree Samarth Developers
THE Berries Studio
possession by Oct 2027 · S Realty LLP
The Beverly Hills
declared completion Nov 2019 · GG Developers
THE Bhanpurawalas
possession by Dec 2028 · THE Bhanpurawalas
THE Business Gate
possession by Oct 2026 · Kesar Vasudev Properties
The Business Hive
declared completion Jan 2021 · M/s. Life Properties

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026