Embassy Springs - Phase 2A, Apartments

EMBASSY DEVELOPMENTS · Devanahalli · K-RERA PRM/KA/RERA/1250/303/PR/180526/001825

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
Litigation on file
Legal status
14
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

826
Registered units
₹339.8 Cr
Est. construction cost
Units profiled
31
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units826Total inventory registered with K-RERA.
Registered land area31,461 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.5Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings5Official tower/wing count in the K-RERA detail page.
Parking disclosed1,029 total (334 open) — 1.25 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date20-02-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Gardenia14252345-
Hibiscus14112158-
Fucshia14112158-
Daisy14196213-
Elderberry14154155-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 406 official flat/unit rows vs 826 registered units disclosed above; ask why the row count differs. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
Other30838.2-84.7 sqm21.6-49.9 sqm308
Others9838.2-84.7 sqm21.6-49.9 sqm98

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Daisy9838.2-84.7 sqm21.6-49.9 sqm98
Elderberry9860.8-84.7 sqm35.2-49.9 sqm98
Gardenia9838.2-75.4 sqm21.6-45.8 sqm98
Fucshia5660.3-82.8 sqm35.1-49.6 sqm56
Hibiscus5660.3-82.8 sqm35.1-49.6 sqm56
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
101Gardenia1Other75.4 sqm44.0 sqm1
102Gardenia1Other75.4 sqm44.4 sqm1
103Gardenia1Other42.0 sqm24.7 sqm1
104Gardenia1Other38.2 sqm21.6 sqm1
105Gardenia1Other67.3 sqm39.9 sqm1
106Gardenia1Other59.7 sqm35.0 sqm1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~726 sqft — compact homes (1–2BHK / studio territory), not compact stock. This is a large, multi-tower township — 826 homes across 5 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 1,029 parking spaces for 826 homes (~1.2 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~39 sqm per home; across all 826 homes that is ~103% of the plot — a healthy sign: buyers collectively hold close to all the land. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

⚠ 32 litigation cases on record

1 of 25 compliance document slots are filed as Not Applicable; the remaining 24 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 28 Feb 2023 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (5 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
NARASIMHA SASTRY VASANTH vs EMBASSY SPRINGS PHASE 2Return of money paid of Rs 5.90 Lakhs + interest for the period till date @18% PA. No agreement or booking form executed.AUTHORITY31/10/2023
Prajit S Nair vs NAM Estaes Pvt Ltd.Request clarification on Rs.30000 which ws forefeitedAUTHORITY21/02/2023
ASHITA GUPTA vs NAM ESTATES PRIVATE LIMITEDRefund of the advance amount of Rs. 8,52,334/- along with 18% interest from the date of payment till realisation.AUTHORITY06/03/2025
Babu Shravani puri vs Emphasis Spring Phase 2AOrder to refund Rs. 8,06,350 with applicable interest and compensation for the delay & agony causedAUTHORITY03/12/2024
P. MAHESH SHANMUGAM & LAKSHMI MAHESH vs NAM ESTATES PRIVATE LIMITEDrefund of the amount paid initiallyAUTHORITY02/05/2024

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 1 project professional/vendor row across Architect. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectSynergy Property Development Private Limited-200Intermediate Ring Road, Kormangala

Builder track record

RERA filing

Embassy has 14 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Embassy Developments”) (average reported construction progress 46%). 4 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹29.90 Cr collected from buyers, ₹18.80 Cr withdrawn from the project's escrow account.

Construction progress61% → 66% (+5 pts)
Units sold/booked as registered624/826 (76%)
Buyer collections in available QPRs₹51.04 Cr
Escrow withdrawals in available QPRs₹30.97 Cr (0.61x collections)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹41.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

Location & Connectivity

The nearest major job hub is ~18 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Kempegowda Int'l Airport9 km
Outer Ring Road / Manyata18 km
MG Road / city centre25 km
Whitefield IT hub29 km
Bellandur–Marathahalli belt31 km
Electronic City40 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Embassy Developments. View Embassy Developments's full track record →
Embassy Developments has 7 projects registered in Bangalore, 1 past RERA deadline.

Other projects by this builder in Bangalore

Embassy Greenshore
Filing overdue · 8% built · 64% sold
Embassy Paradiso
Filing overdue · 80% built
Embassy Verde
Filing overdue · 17% built · 90% sold
Embassy Verde
Filing overdue · 17% built · 90% sold
Embassy Verde Phase 2
Filing overdue · 1% built · 88% sold
Embassy Springs - Phase 2a, Apartments
Filing overdue · 66% built · 76% sold

Other RERA-registered projects in Devanahalli

Under The Sun – Luxury Villa Lifestyle By Fortius
Construction Of 423 Houses In Vijayappura & Devan

Major developers building in Devanahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Embassy Springs - Phase 2a, Apartments?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 27 Jul 2026