MahaRERA Property Intelligence · Pune

BALAJI RESIDENCY

P52100046332 · BALAJI RESIDENCY, PLOT NO 33, SR NO 31/2B/32, DHANKUDE NAGAR, BANER · promoter Balaji Developers

Certificate SignedDue 30 Jun 2024

Delivery & Registration

MahaRERA registrationP52100046332
Registered on22 Jun 2022
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
BALAJI RESIDENCY1G+431 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202330 Jun 2024Original Building Plan earlier was upto 6 flat now it has been revised for 10 flats and due to delay in revised approval we have to revised date of completion till 30th June 2024

Location, Land & Connectivity

Located at BALAJI RESIDENCY, PLOT NO 33, SR NO 31/2B/32, DHANKUDE NAGAR, BANER, PAN CARD CLUB ROAD, Haveli, Pune, 411045. Per the filed land record, the plot is bounded to the north by PLOT NO 32 OF SR NO 31 2B 2, to the south by PROPERTY OUT OF SR NO 18, to the east by 20 FEET COMMON ROAD BEYOND THAT PLOT NO 31 and to the west by PROPERTY OUT OF SR NO 32. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre2 km
Magarpatta / Hadapsar IT7 km
Kharadi / EON IT Park9 km
Baner–Balewadi belt9 km
Pune Int'l Airport (Lohegaon)10 km
Hinjewadi Rajiv Gandhi IT Park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Balaji Developers is the promoter on 22 MahaRERA-registered projects, of which 5 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Balaji Developers project & its RERA track record →

Other flagged projects by Balaji Developers

Balaji Developers
Past its declared completion datePune
Balaji Developers
Past its declared completion datePune
Balaji Developers
Past its declared completion datePune

Other RERA-registered projects in Baner

7 Business BAY
possession by Jul 2026 · Saaj Buildcon Private Limited
Maitreya
Not filing quarterly progress reports · possession by Jul 2026 · Vaibhav Shamrao Taro
Mercury
possession by Aug 2026 · SB Real Estate Private Limited
Aarambh
possession by Aug 2026 · ADI Realtors
Nancy Hillview A-1
possession by Aug 2026 · M/S Sarsan Aawishkar Properties
Truspace Platina
possession by Aug 2026 · Atharva Developments

Major developers building in Baner

Other RERA-registered projects in Pune

Balaji Residency
possession by Dec 2026 · Shree Balaji Properties
Balaji Serenity
declared completion Dec 2024 · Balaji Buildcon
Balaji Siddhi
possession by Oct 2027 · Shri Balaji Siddhi Developers
Balaji Vishwa
declared completion Jun 2023 · Ideal Developers
Balaji Vishwa
declared completion Oct 2021 · Balaji Developers
Balaji Vishwa Building C
declared completion Dec 2022 · Ideal Properties

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026