Bangalore/Project record

K-RERA · the public record

Bhartiya Garden Estate Phase-3

Bengaluru North · Bhartiya Urban

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

42%construction reportedQ1 2026 filing
263units not bookedof 543 · Q1 2026 filing
31 Aug 2031declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Aug 2031

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Residential - Apartments
543

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

28.6registered acres

19.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/309/PR/060925/008065

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 August 2031
Land area115,738 sq m (28.6 acres)
Homes registered543
Tower/wing entries3
Unit mix543 × Residential - Apartments

In context

Density19 homes per acre
Density in context10th percentile of 525 Bengaluru North projects (median 75.4)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units543Total inventory registered with K-RERA.
Official carpet area48,388 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area107,787 sqmUseful scale context when comparing density and project cost.
Registered land area115,738 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.5Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)566Separate filed counts; these categories may overlap and are not added together.
Covered-parking field566Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBIAAPA/TP/CC/219/2025-26Use this to match the sanctioned drawing set shown by the builder.
Plan approval date06-08-2025
Project start date01-09-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Residential - Apartments543100%48,388 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower E2220322668.1 m
Tower F2216016068.1 m
Tower G2218018068.1 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 543 official flat/unit rows, matching the 543 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2.5 BHK13477.6-81.9 sqm32.9-34.2 sqm134
3 BHK130101.8-109.4 sqm42.7-45.2 sqm130
2 BHK9664.3-68.3 sqm27.6-28.8 sqm96
3.5 BHK69121.9-122.8 sqm50.2-50.4 sqm69
1 BHK4643.1 sqm19.4 sqm46
4 BHK23153.4 sqm63.5 sqm46
Studio2335.5 sqm13.7 sqm23
LOFT20126.8 sqm54.1 sqm20
1.5 BHK273.4 sqm31.0 sqm2

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower E20335.5-153.4 sqm13.7-63.5 sqm226
Tower G18043.1-122.8 sqm19.4-50.2 sqm180
Tower F16065.8-126.8 sqm28.1-54.1 sqm160
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
E0003Tower E02.5 BHK77.6 sqm32.9 sqm1
E0004Tower E02 BHK68.3 sqm28.8 sqm1
E0005Tower E0Studio35.5 sqm13.7 sqm1
E0006Tower E01 BHK43.1 sqm19.4 sqm1
E0007Tower E02 BHK64.3 sqm27.6 sqm1
E0008Tower E03.5 BHK121.9 sqm50.4 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

7 of 34 compliance document slots are filed as Not Applicable; the remaining 27 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (11 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190215/0002134
15-02-2019
Inferiror unusable car park allotement, betrayal of trust, delay compensation, GST benefits not transferred to customers, unaddressed quality issuesNikoo Homes I (Towers 1 - 6 & 10) (another project by this promoter)DISPOSED AO
CMP/191118/0004752
18-11-2019
Non-Payment/denial of Refund of advance amount after cancellation of bookingBhartiya Leela Residences (another project by this promoter)DISPOSED AO
CMP/191203/0004833
03-12-2019
Interest against pending paymentNikoo Homes I (Towers 1 - 6 & 10) (another project by this promoter)DISPOSED AO
CMP/200225/0005545
25-02-2020
Delay CompensationNikoo Homes I (Towers 1 - 6 & 10) (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/200611/0006015
11-06-2020
Delay CompensationNikoo Homes I (Towers 1 - 6 & 10) (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/200726/0006254
26-07-2020
Builder trying to cancel apartment due to non-payment if dues in old terms before rera registeredNikoo Homes II West (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/200731/0006278
31-07-2020
Carpet area is delivered lessNikoo Homes I (Towers 1 - 6 & 10) (another project by this promoter)DISPOSED AO
CMP/200909/0006547
09-09-2020
Delay CompensationNikoo Homes I (Towers 1 - 6 & 10) (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved13-12-2023Water NOC 13 12 2023.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved30-12-2024Pollution control Board 30 12 2024.pdf
KPTCL- BESCOMApproved25-04-2024BESCOM 25 04 2024.pdf
Fire and SafetyApproved09-07-2025Fire 09 07 2025.pdf
Airport Authority of IndiaApproved29-11-2023Airport Authority of India 12 2 and 13(P) NOC 15 11 2023.pdf
BSNL/Telecommunication DepartmentApproved15-03-2024BSNL 15 03 2024.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantAnand Rao V J2086702011Bengaluru Urban, Karnataka - 560070
EngineerH P YogeshBCC – BL/3.6-STRL.E.67:09-102010Bengaluru Urban, Karnataka - 560078
ArchitectDeepa S AthaniC.A/2010/502972010Bengaluru Urban, Karnataka - 560077
ContractorUrbanac Projects Pvt Ltd-2015Bengaluru Urban, Karnataka - 560064

Builder track record

RERA filing

Bhartiya Urban has 15 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Bhartiya Urban”) (average reported construction progress 56%). 4 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹25.36 Cr collected from buyers, ₹25.36 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹25.36 Cr) exceeded buyer collections (₹25.36 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress3% → 42% (+39 pts)
Units sold/booked as registered280/543 (52%)
Buyer collections in available QPRs₹42.42 Cr
Escrow withdrawals in available QPRs₹41.73 Cr (0.98x collections)
  • Construction progress moved from 3% to 42% across the filed QPR window.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹53.5 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: STATE BANK OF INDIA Commercial Branch IFSC Code : SBIN0004196 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Kempegowda Int'l Airport7 km
Outer Ring Road / Manyata17 km
MG Road / city centre25 km
Whitefield IT hub28 km
Bellandur–Marathahalli belt30 km
Electronic City39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Bhartiya Urban. View Bhartiya Urban's full track record →
Bhartiya Urban has 15 projects registered in Bangalore, 1 completed.
3 complaints on the K-RERA register against Bhartiya Urban in Bangalore.

Other projects by this builder in Bangalore

Nikoo Homes IV
Filing overdue · 100% built · 100% sold
Bhartiya Garden Estate Phase-1
On track · 38% built · 87% sold
Bhartiya Garden Estate Phase-2
On track · 41% built · 75% sold
Bhartiya Leela Residences
No filings
Nikoo Homes 8, Bhartiya Garden Enclave, Phase-1
On track · 38% built · 21% sold
Nikoo Homes 8, Bhartiya Garden Enclave, Phase-2
On track · 46% built · 0% sold

Other RERA-registered projects in Devanahalli

Under The Sun – Luxury Villa Lifestyle By Fortius
Construction Of 423 Houses In Vijayappura & Devan

Major developers building in Devanahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Bhartiya Garden Estate Phase-3?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026