CALLISTA

citadel projects and developers · · K-RERA PRM/KA/RERA/1257/334/PR/060822/005140

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
2
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

25
Registered units
₹38.4 Cr
Est. construction cost
Units profiled
54
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units25Total inventory registered with K-RERA.
Official carpet area6,320 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area12,629 sqmUseful scale context when comparing density and project cost.
Registered land area1,761 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI4.594Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings1Official tower/wing count in the K-RERA detail page.
Parking disclosed66 total (66 covered, 0 open) — 2.64 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Approved plan numberE4/BA24-2021-22Use this to match the sanctioned drawing set shown by the builder.
Plan approval date07-06-2022
Project start date01-07-2022

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
4 BHK25100%6,320 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
CALLISTA272566104.24 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 25 official flat/unit rows, matching the 25 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
4 BHK25252.8 sqm4.0 sqm66

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
CALLISTA25252.8 sqm4.0 sqm66
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1CALLISTA34 BHK252.8 sqm4.0 sqm2
2CALLISTA44 BHK252.8 sqm4.0 sqm2
3CALLISTA54 BHK252.8 sqm4.0 sqm2
4CALLISTA64 BHK252.8 sqm4.0 sqm2
5CALLISTA74 BHK252.8 sqm4.0 sqm2
6CALLISTA84 BHK252.8 sqm4.0 sqm2

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~2,721 sqft — large, premium-format homes (4BHK/penthouse territory), not compact stock. This is a boutique, low-density project — 25 homes across 1 tower. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 66 parking spaces for 25 homes (~2.6 per home) — comfortable headroom over the 1-per-home many projects offer.
Your land share (UDS)Undivided land share averages ~4 sqm per home; across all 25 homes that is ~6% of the plot — on the lower side — the undivided shares sum to noticeably less than the plot, worth asking the builder why before relying on it. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

21 of 47 compliance document slots are filed as Not Applicable; the remaining 26 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance and pollution-control clearance (KSPCB) are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

7 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
KPTCL- BESCOMApproved29-01-2022MESCOM NOC CALLISTA20220727_15163332.pdf
Fire and SafetyApproved14-01-2022FIRE NOC CALLISTA.pdf
Labour and Education DepartmentApproved08-08-2022LABOUR LICENCE CALLISTA.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantOLVIN HENRY ROADRIGUES2031282000Dakshina Kannada, Karnataka - 575002
EngineerSHILP CONSULTING ENGINEERSSTR-8400139532003Mumbai City, Maharashtra - 400063
ArchitectUPALEKAR SADEKARCA/84/081041988Mumbai City, Maharashtra - 400016
ContractorMFAR CONSRTUCTIONS-1996Bengaluru Urban, Karnataka - 560034

Builder track record

RERA filing

Citadel Projects has 2 other K-RERA-registered projects in our records (average reported construction progress 20%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹8.63 Cr collected from buyers, ₹6.04 Cr withdrawn from the project's escrow account.

Construction progress80% → 90% (+10 pts)
Units sold/booked as registered17/25 (68%)
Buyer collections in available QPRs₹9.00 Cr
Escrow withdrawals in available QPRs₹6.30 Cr (0.70x collections)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹153.5 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Bank of Baroda BEJAI IFSC Code : BARB0VJBIJA Pin Code : 575004. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Outer Ring Road / Manyata11 km
Whitefield IT hub11 km
Bellandur–Marathahalli belt14 km
MG Road / city centre15 km
Kempegowda Int'l Airport15 km
Electronic City25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Citadel Projects.
Citadel Projects has 3 projects registered in Bangalore.

Other projects by this builder in Bangalore

Antares
Filing overdue · 20% built · 45% sold

Other RERA-registered projects in Krishnarajapuram

Trifecta Verdeen Resplandor ROW House Phase-3

Major developers building in Krishnarajapuram

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.