MONTECITO
Bengaluru East · IMPERIAL DWELLINGS AND WHITEFIELD LUXURY VILLAS
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Promoter-reported construction
K-RERA quarterly filings · Q4 2025 to Q4 2025
declared completion
01 Apr 2032
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1251/446/PR/060126/008384
This project, on the record
The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.
On the register
Values as crawled from the official K-RERA record; context percentiles name their comparison population.
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Approved plan number | BDA-PRL-40/2022-23/2508/2024-25 | Use this to match the sanctioned drawing set shown by the builder. |
| Plan approval date | 03-01-2025 | |
| Project start date | 01-04-2025 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingNo litigation declared on this project's K-RERA filing.
⚠ 2 of 19 compliance document slots are filed as under process / not yet usable: Board Resolution for Authorized Signatory/Certificate of Authorization, Relinquishment Deed.
2 additional compliance slots are filed as Not Applicable.
No completion certificate (OC) on file yet — project has not been declared complete.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
Statutory approval status
RERA filing2 of 3 applicable approvals are on file; still outstanding: KSPCB- PCB (10 Acres to 125 Acres). Pollution-control clearance (KSPCB) is among them — a high-importance clearance, so confirm it has been granted (not just applied for) before you book.
8 further authority slots are marked not applicable by the regulator.
| Authority / NOC | Status | Date | File |
|---|---|---|---|
| Water supply and sewage board | Approved | 28-01-2025 | Water NOC.pdf |
| KSPCB- PCB (10 Acres to 125 Acres) | Applied | 26-02-2025 | View NOC |
| KPTCL- BESCOM | Approved | 11-02-2025 | Bescom.pdf |
Project team & certifications
RERA filingK-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Chartered accountant | Vinay G Lal | 219133 | 2010 | Bengaluru Urban, Karnataka - 560001 |
| Engineer | P Bhaskar Reddi | BCC/BL-3.6/E-4130/2015-16 | 2015 | Bengaluru Urban, Karnataka - 560077 |
Builder track record
RERA filingImperia has 3 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Imperial Dwellings”) (average reported construction progress 87%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.
Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.
Financials & Construction Progress
Financial disclosures
RERA filingLatest quarterly filing (2025-Q4): ₹1.52 Cr collected from buyers, ₹0.95 Cr withdrawn from the project's escrow account.
| Construction progress | 76% → 76% (+0 pts) |
| Buyer collections in available QPRs | ₹1.52 Cr |
| Escrow withdrawals in available QPRs | ₹0.95 Cr (0.62x collections) |
- The builder has drawn 0.62x of buyer collections from escrow (about 62% of the ₹2 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.
QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.
The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.
RERA 70% project account is on file: YES BANK Marathahalli IFSC Code : YESB0000931 Pin Code : 560037. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Location & Connectivity
The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Whitefield IT hub | 6 km |
| Bellandur–Marathahalli belt | 13 km |
| Outer Ring Road / Manyata | 17 km |
| MG Road / city centre | 19 km |
| Kempegowda Int'l Airport | 22 km |
| Electronic City | 23 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.